BOXER SERIES80-120 KVA
INSTALLATION
AG-SD-37/ Publication Date: 19.10.2012/Rev. No:1/Rev. Date:16.11.2012
23
3 INSTALLATION
3.1 Single Module Installation
In this section, warnings which you must follow and the checks which you must perform before
starting-up the device are stated. Additionally, you can find information concerning the points
you must pay attention to during carrying style for cabinets, positioning and connections.
3.1.1 Warnings
The UPS must be installed by the personnel approved by MAKELSAN.
Warranty is not valid for the devices installed by unauthorized personnel.
Battery Hazard!
In some models, during operation of battery and the UPS together, there may exist battery
terminal voltages reaching up to 450 VDC.
Precautions must be taken in order to protect eyes against electrical arcs that can result from
contacts.
ESD-protected rubber gloves should be used.
Batteries discharging or leaking electro liquid must not be used, if any, it must be replaced.
Uninstalled batteries must be kept, carried and transferred to destruction points safely.
In case of skin contact with elector liquid, immediately rinse the exposed skin part with water.
Operator must remove any dangerous accessories such as ring, watch etc. before working on the
device.
The product needs three phase and four cable (+ground) supply system for input. Type of this
supply system conforms to IEC60364-3 standards. The devices have transformers which have
ability to optionally convert from three cable to four cable system. Provided that IT AC power
distribution will be installed, 4 pole-circuit breaker must be used. More detailed explanations
concerning the topic can be found in the standard named as IEC60364-3.