4
74D0010
VENT INSTALLATION
3. Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in
roof). The 9
1
/
2
"x9
1/2
" (241mm x 241mm) hole must be measured on the horizontal. Actual length may be larger depending
on the pitch of the roof. There must be a 1" minimum clearance from the vent pipe to combustible materials. (Insulation
should be considered a combustible material).
4. Connect a section of pipe and extend up through the hole.
NOTE: If an offset is needed to avoid obstructions, you must support the vent pipe every three (3) feet.
Use wall straps for this purpose. See Figure 23, page 22. Whenever possible, use 45° elbows instead of
90° elbows. The 45° elbow offers less restriction to the flow of the flue gases and intake air.
5. Place the flashing over the pipe section(s) extending through the roof. Secure the base of the flashing to the roof and
framing with roofing nails. Be sure roofing material overlaps the top edge of the flashing. There must be a 1" clearance
from the vent pipe to combustible materials.
6. Continue to add pipe sections until the height of the vent cap meets the minimum building code requirements.
NOTE: You must increase vent height for steep roof pitches. Nearby trees, adjoining roof lines, steep
pitched roofs, and other similar factors may cause poor draft or down-drafting in high winds. Increasing
the vent height may solve this problem.
NOTE: If the vent pipe passes through any occupied areas above the first floor, including storage spaces
and closets, you must enclose pipe. You may frame and sheetrock the enclosure with standard construction
material. Make sure to meet the minimum allowable clearances to combustibles. Do not fill any of the
required clearance spaces with insulation.
ROOF PITCH
H (feet)
Flat to 6/12
1.0
Over 6/12 to 7/12
1.5
Over 7/12 to 8/12
1.5
Over 8/12 to 9/12
.0
Over 9/12 to 10/12
.5
Over 10/12 to 11/12
3.5
Over 11/12 to 12/12
4.0
*H = Minimum height from roof to lowest
discharge oopening of vent.
Figure 28 - Minimum Chimney Clearance
Содержание 400DVBL
Страница 52: ...52 74D0010 2 3 4 5 6 7 illustrated parts lists firebox components ...
Страница 54: ...54 74D0010 illustrated parts lists 1 2 3 4 5 6 7 8 10 11 12 13 14 Standing Pilot Millivolt control 2T 2I 2C 8 ...
Страница 56: ...56 74D0010 illustrated parts lists SIGNATURE COMMAND SYSTEM 0009 SG parts 8 08 1 2 3 4 17 5 6 7 8 9 13 14 15 ...
Страница 64: ...64 74D0010 SEPTEMBER 2008 74D0010 Rev 10 MHSC 149 Cleveland Drive Paris Kentucky 40361 www mhsc com ...