6.3.2.  Maintenance of the boiler block 

 
 

In  order  to  ensure  the  complete  combustion  of  fuel  and  thereby  optimal  boiler 

efficiency,  it  is  recommended  to  maintain  the  appropriate  cleanness  of  the  walls  of  the 
combustion  chamber,  the  smoke  tubes  of  the  heat  exchanger,  and  the  reversal  chambers. 
To this end: 
 

 

Switch  off  the  burner,  pumps  and  power  supply  on  the  control  panel.  Remove  the 
plug of the power lead from the electrical outlet. 

 

Disconnect plugs which connect the burner electrically with the boiler. 

 

If necessary, remove the burner. Burner maintenance and adjustments are separate 
operations,  and  have  been  described  in  detail  in  the  instruction  and  user  manual 
delivered together with the burner. 

 

Remove  the  locking  screws  and  open  the  front  door  of  the  burner  in  order  to  gain 
access to the combustion chamber and the smoke tubes. 

 

Remove  the  flue  gas  turbulators  (coils)  from  the  smoke  tubes.  Use  a  round  steel 
brush  seated  on  a  cleaning rod to  carefully  clean  the smoke  tubes  and the  reversal 
chamber of contaminants.  

 

Using the steel brush, carefully clean the combustion chamber of contaminants.  

 

Check the seals of the front door.  

 

Clean  the  flue  gas  turbulators  with  the  seal  brush  and  replace  them  in  the  smoke 
tubes. Assemble the components of the boiler by performing the disassembly steps in 
reverse order. 

 

Remove the screw of the rear washout hole. Remove the cover, empty the trays and 
carefully clean the flue gas exhaust chamber of contaminants (a vacuum cleaner may 
be used for this purpose). Check the seals, slide in the trays and replace the washout 
hole cover. Screw down the locking screws. 

 

Figure No. 11. Elements of the boiler block which require maintenance 

 

 

 

 

A – Flue gas turbulator (coil) 

 

E – Combustion chamber 

Содержание BIO-MAX PLUS

Страница 1: ...N MANUAL ul G wna 51 B Krosno 62 Heating boiler with automatic fuel delivery BIO MAX PLUS Series of types 70 300 kW TECHNICAL INSTRUCTION USER MANUAL AND INSTALLATION MANUAL LUMO Technika Grzewcza Sp...

Страница 2: ...quality 14 4 7 Connection to the electrical system 14 4 8 Connection to the domestic hot water exchanger option 17 4 9 Connection of the boiler to a chimney stack system 18 5 OPERATION 19 5 1 Prepara...

Страница 3: ...constant development and improvement of our products we would ask you to send us all and any comments concerning the functioning of our appliances and the level of service provided by our partners We...

Страница 4: ...two weeks of the date of initial start up shall void the guarantee for your newly purchased appliance thus resulting in the user being required to cover the entirety of costs of all and any repair wor...

Страница 5: ...hen there is a risk of water freezing in the system Water should also be drained in the event of a leak which may result in flooding ATTENTION It is forbidden to tamper with safety devices Only origin...

Страница 6: ...e of their nature and scope may be carried out solely following disconnection of the power supply Further repairs may be carried out EXCLUSIVELY by the Authorised Service Centre or duly authorised per...

Страница 7: ...t while in the upper part is a large and easily accessible washout hole which facilitates cleaning of the heat exchanger and the smoke tubes A tray for ash is located in the bottom part of the boiler...

Страница 8: ...8 Figure No 2 Component elements of the boiler Figure No 2 Component elements of the boiler...

Страница 9: ...9...

Страница 10: ...10 3 2 Technical parameters Figure No 3 Boiler installation dimensions...

Страница 11: ...factured in accordance with PN EN ISO 17225 2 2014 07 Voltage V Hz 230 50 Electrical terminal A 6 Power consumption in standby W 3 Power consumption under nominal operating conditions W 234 278 630 66...

Страница 12: ...ther the phase conductor L is correctly located and whether the outlet has a ground terminal that is in good working order 4 2 Location of the boiler The boiler should be located in a separate room pu...

Страница 13: ...775 4 3 Installation of the burner Installation of the burner consists solely in attaching it by means of screws to the boiler door The pertinent detailed technical information screw thread diameters...

Страница 14: ...n Table No 1 These stub connectors and their corresponding joints are used to connect the boiler to the central heating system in the appropriate manner so as not to mix up supply with return for exam...

Страница 15: ...required 4 6 Guidelines concerning water quality The quality of water used to fill the boiler and the system is of critical importance for their longevity and trouble free operation Inappropriate boil...

Страница 16: ...16 Figure No 7 Wiring diagram ecoMAX860P Standard and ecoMAX860P Touch...

Страница 17: ...eather based temperature sensor type CT6 P RS return water temperature sensor type CT4 FS feeding mechanism temperature sensor type CT4 OS optical flame brightness sensor BT boiler temperature sensor...

Страница 18: ...RM2 room thermostat mixer 2 RM3 room thermostat mixer 3 L N PE power supply 230 V GR grounding strip PM2 PM3 pump mixer 2 3 SM2 SM3 servo motor mixer 2 3 CPU control A executory module of the ecoMAX8...

Страница 19: ...ned by the duly authorised system designer The following figure presents an exemplary diagram of a system comprising a LUMO WCW hot domestic water exchanger and a Bio max Plus boiler Figure No 10 Exem...

Страница 20: ...cts being released by the boiler into the boiler room and the concentration of CO in the combustion chamber While Bio max Plus boilers operate in their lower power range the temperature of flue gases...

Страница 21: ...e boiler it is necessary to perform a fresh inspection of the appliance and its ancillary devices and in particular to carry out an internal inspection of the boiler water filling inspection to carry...

Страница 22: ...manuals delivered together with these two devices During initial start up there may occur the phenomenon of boiler sweating In this event it will be necessary to intensify the combustion process in o...

Страница 23: ...its ancillary devices at least once a year preferably before the start of the heating season The entirety of repairs inspections adjustments and maintenance may be performed solely by the Authorised S...

Страница 24: ...ce a year every 12 months Inspection of the functioning of regulating and safety devices including the safety valve and the safety temperature limiter STB Inspection of the ventilation system Inspecti...

Страница 25: ...urner in order to gain access to the combustion chamber and the smoke tubes Remove the flue gas turbulators coils from the smoke tubes Use a round steel brush seated on a cleaning rod to carefully cle...

Страница 26: ...y of activities described under the present point are to be performed solely by the Authorised Service Centre 6 4 1 General guidelines During each inspection and maintenance operation performed on the...

Страница 27: ...manufacturer must be followed at all times during such checks All and any failures caused by the incorrect functioning of the burner or brought about intentionally are displayed on the control panel...

Страница 28: ...s and leads The controller has got damp Damaged display Check the electrical connection of the boiler Check the correctness of installation of plugs and whether the controller has been properly connec...

Страница 29: ...29...

Отзывы: