Lucent Technologies Lineage
®
2000 ECS Battery Plant H569-403
4 - 8 Installation
Issue 4 February 1997
AC Wiring,
Rectifier
Installation and
Test
Refer to the installation and start-up procedure in the Rectifier
manual for the following steps.
•
Wire AC
•
Set up
•
Plug in
•
Test
Before proceeding, verify that all rectifier output circuit breakers
are in the OFF position.
Load Wiring
Open the dc distribution cover panel by turning the two 1/4 turn
fasteners located on the front of the panel.
Run paired leads (supply and return) to each load from a dc
distribution circuit breaker or fuse and from the discharge return
bus. The load supply leads are terminated at the breaker and fuse
panels (directly to the breaker or fuse terminal end). The load
return leads are terminated at the battery plant end on the
discharge return bus, located at the top front of the bus bar
arrangement.
Recommendations for routing and dressing of load leads as they
leave the battery plant and enter the cable rack system are shown
on the plant assembly drawing, H569-403 or in Figure 3-4.
Consult the job application drawings for the routing of these
leads to the load equipment.
Before proceeding, verify that all load circuit breakers are in the
OFF position.
Note
AC wiring should be completed during the initial installation for
all rectifier positions that may be used in the future. If ac is
prewired in this way, growth in rectifier capacity is as simple as
plugging in an additional rectifier. It will also be possible to add
a rectifier without shutting down adjacent rectifiers to gain
access to space for additional ac wiring.
DANGER
Verify that no voltage is present on the dc distribution bus bars
and that all dc circuit breakers are off before connecting any
load leads.