EQUIPMENT GAS SYSTEM LEAK CHECK
An approved gas-inlet appliance isolating valve and union should be installed for each unit in a convenient and
safe position and be clearly marked. Ensure that the gas-inlet appliance isolating valve is in the OFF position.
Although the equipment receives a gas leak check and gas train component integrity check prior to leaving the factory,
transit and installation may cause disturbance to unions, fittings and components. During commissioning a further test
for tightness should be carried out on the equipment gas pipework and components.
Care must be taken not to allow leak detection fluid on or near any electrical parts or
connections.
Содержание HERALD HCB116CE
Страница 8: ...8 3 1 2 PRINCIPLE PARTS TO BE USED IN CONJUNCTION WITH TABLE 3 1 1...
Страница 11: ...11 5 2 CLEARANCES 5 2 1 ENCLOSURE INSTALLATION CLEARANCES MM 5 2 2 PLANT ROOM INSTALLATION CLEARANCES MM...
Страница 31: ...31 Max distance between brackets...
Страница 32: ...32...
Страница 33: ...33...
Страница 37: ...37...
Страница 53: ...53 15 8 WIRING DIAGRAM 15 8 1 WIRING DIAGRAM...
Страница 54: ...54 15 9 LADDER DIAGRAM 15 9 1 LADDER DIAGRAM...
Страница 92: ...92...