Temporary Interruption of Crane Operations
As a general rule, if it is not possible to maintain sufficient control over a rigged crane, the boom and the
equipment shall be taken down if the crane’s operations are interrupted and may be left unsupervised�
The following instructions are valid for every mobile crane, regardless of the type, the configuration, the
rigging mode and the environment:
• The crane shall be left in the smallest, most stable, valid operational configuration that the job site
practically allows; this includes parameters such as boom angle, slewing orientation, jib angle�
• The engines shall be switched off�
• All control levers shall be put into the neutral or in a “locked” position�
• The heating system should be switched off�
• The crane shall be secured and the cabins shall be locked to prevent unauthorized use or unintended
movement�
• Close all control panels that are fitted with a lock/key when they are not in use�
• Depending on the crane type, mobile control panels connected to the crane with cables shall be
removed when they are not in use�
• The radio remote control, if it is available, shall be kept in a safe place to prevent unauthorized use
or unintended movement� Make sure that the batteries are recharged�
• The parking brake of the crane chassis shall be applied�
• Transmission gear shall be set to neutral�
• The wheels shall be secured with chocks, the slew brake applied and the main boom secured�
If the crane is in erected mode and the jobsite conditions do not permit the boom and jib of a crane to
be fully lowered to the ground, the configuration in which the crane should be left while unmanned shall
be determined by a qualified crane operator familiar with the crane, the job site configuration, conditions,
and limitations� In addition, following instructions shall be observed:
• A suitable and safe emergency plan shall be worked out to allow bringing the crane into a safe
position in case of emergency such as an unforeseen weather change or other possible incidents
as listed at the beginning of this document� This plan shall also include sufficient space around the
crane to enable dismantling or lowering of boom or equipment, etc�
• The crane shall be left with no load on the hook�
• All slings or fastening ropes shall be removed from the crane hook�
• The hook block shall be at the highest position so that there is no contact possible between the
wire ropes and the boom or other obstacles�
• The crane location and configuration does not create hazards to the road traffic, e�g� risk of collision
with surrounding obstacles; this may require a specific risk assessment prior to leaving the crane
unattended�
Содержание 35-127 M
Страница 1: ...OPERATORS MANUAL LOAD KING 35 127 M C1046093 REV A FEBRUARY 09 2022...
Страница 2: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 48: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 63: ...63 Description Of Machine and Controls Operator Controls 5 3 2 4 8 7 1 9 10 6...
Страница 79: ...79 REPAIRS ADJUSTMENTS REMARKS ITEM REQUIREMENT DATE...
Страница 96: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 109: ...109 Boom Angle Placards CAUTION Do not extend jib into this area unless boom is fully retracted...
Страница 124: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 131: ...131 35 127 M Master Lube Chart 1 2 5 11 12 3 4 6 8 9 7...
Страница 132: ...132 35 127 M Maintenance...
Страница 150: ...150 35 127 M Maintenance...
Страница 172: ...PAGE INTENTIONALLY BLANK...
Страница 176: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 201: ...201 Repairs Adjustments Remarks Log ITEM REQUIREMENT DATE...
Страница 202: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 209: ...209 Torque Specs SAE Metric...
Страница 210: ...210 35 127 M Appendix...
Страница 212: ...PAGE INTENTIONALLY LEFT BLANK...
Страница 213: ...Notes...
Страница 216: ...35 127 M Operator Manual...