Touch Screen Display
109
5. Select DELAY.
A keypad is displayed prompting you for a delay time, in seconds, for a condition to exist before
the alarm is triggered.
6. Enter the delay value. The range for the values are from 0 (zero) to 99.9 seconds.
7. Select OK on the keypad to keep your setting.
The value you entered is displayed in the field adjacent to the corresponding input contact.
8. Repeat
Steps 2
to
7
for each input contact.
9. Select SAVE after you have configured all input contacts.
Be sure to select Save even if you have accessed this dialog only to change a setting.
10. Enter the settings in
Table 32 - Input contact isolator settings record
.
This information is not saved if control power is removed.
11. Select OK in the Comm Options dialog box to activate the settings.
Configuring the Programmable Relay Board Settings
The STS2/PDU can contain up to two programmable relay boards (PRB) that can trigger an external
device when an event occurs in the Static Transfer Switch 2 Power Distribution Unit. For example, if
Source 1 fails, an external light flashes.
See
6.1 - Programmable Relay Board
for more information on the PRBs.
The programmable relay board dialog box with two options: STANDARD SET and USER DEFINED
SET. The STANDARD SET are the factory-configured settings.
The STANDARD SET for the programmable relay board settings are:
The USER DEFINED SET allows you to assign faults and alarms to each contact on the relay boards.
Utilizing the USER DEFINED SET, you can also select Input Contact Isolators to associate with a
programmable relay.
In addition individual events, three other assignment choices are available:
• SELECT ALL sends a summary event to the selected relay whenever any event occurs. If this set-
ting is selected for a relay, no other event needs to be assigned for that relay.
• ON SOURCE 1 or ON SOURCE 2 can be assigned to a relay to send a notification when that
source is being used by the load.
Once configured, the Static Transfer Switch 2 Power Distribution Unit continuously checks the status
of the items defined for each contact and updates the state of the relay.
Table 19
Standard settings for programmable relays
Relay
Setting
Definition
1
SOURCE 1 FAIL
Source 1 failure
2
SOURCE 2 FAIL
Source 2 failure
3
BYPASS CB4 CLOSED
Switch (CB4) is closed; Source 1 is bypassed.
4
BYPASS CB5 CLOSED
Switch (CB5) is closed; Source 2 is bypassed.
5
TRANSFER INHIBIT
A transfer between Source 1 and Source 2 is being restrained.
6
OUT OF SYNC
The phase difference between sources 1 and 2 exceeds the
allowable threshold for transfer.
7
EQUIP OVER TEMP
The ambient temperature of the ProductName
exceeds the
recommended threshold for operation.
8
Blank
No setting
Содержание PDUTM
Страница 1: ...POWER DISTRIBUTION STS2 PDU INSTALLATION OPERATION MAINTENANCE MANUAL 250A 800A Three Phase 60 Hz ...
Страница 25: ...Installation Drawings 17 7 0 INSTALLATION DRAWINGS Figure 7 Outline drawing 250A STS2 PDU ...
Страница 26: ...Installation Drawings 18 Figure 8 Outline drawing 250A STS2 PDU with right side I Line distribution ...
Страница 27: ...Installation Drawings 19 Figure 9 Outline drawing 250A STS2 PDU with right side inline distribution ...
Страница 28: ...Installation Drawings 20 Figure 10 Outline drawing 250A STS2 PDU with left side I Line distribution ...
Страница 29: ...Installation Drawings 21 Figure 11 Outline drawing 250A STS2 PDU with left side Inline distribution ...
Страница 30: ...Installation Drawings 22 Figure 12 Outline drawing 400 600A STS2 PDU with right side inline distribution ...
Страница 32: ...Installation Drawings 24 Figure 14 Outline drawing 400 600A STS2 PDU with left side inline distribution ...
Страница 35: ...Installation Drawings 27 Figure 17 Outline drawing 800A STS2 PDU with right side inline distribution ...
Страница 37: ...Installation Drawings 29 Figure 19 Outline drawing 800A STS2 PDU with left side inline distribution ...
Страница 38: ...Installation Drawings 30 Figure 20 Outline drawing 250A STS2 PDU with key lockout switch option ...
Страница 41: ...Installation Drawings 33 Figure 23 Electrical field connections 250A STS2 PDU input output with CB8 ...
Страница 42: ...Installation Drawings 34 Figure 24 Electrical field connections 250A STS2 PDU input with CB3 ...
Страница 43: ...Installation Drawings 35 Figure 25 Electrical field connections 250A STS2 PDU input with CB3 CB3A ...
Страница 44: ...Installation Drawings 36 Figure 26 Electrical field connections 400 600A STS2 PDU input with CB3 ...
Страница 45: ...Installation Drawings 37 Figure 27 Electrical field connections 400 600A STS2 PDU input with CB3 and CB3A ...
Страница 46: ...Installation Drawings 38 Figure 28 Electrical field connections 800A STS2 PDU input with CB3 ...
Страница 47: ...Installation Drawings 39 Figure 29 Electrical field connections 800A STS2 PDU input with CB3 and CB3A ...
Страница 48: ...Installation Drawings 40 Figure 30 Electrical field connections 250A STS2 PDU output with inline panelboards ...
Страница 50: ...Installation Drawings 42 Figure 32 Electrical field connections STS2 PDU output with I Line panelboard ...
Страница 53: ...Installation Drawings 45 Figure 35 Electrical field connections 800A STS2 PDU with right side output breaker ...
Страница 54: ...Installation Drawings 46 Figure 36 Electrical field connections 8600A STS2 PDU with left side output breaker ...
Страница 55: ...Installation Drawings 47 Figure 37 Electrical field connections 800A STS2 PDU interconnect wiring ...
Страница 57: ...Installation Drawings 49 Figure 39 Electrical field connections 800A STS2 PDU interconnect wiring STS section ...
Страница 63: ...Installation Drawings 55 Figure 45 Control wiring 800A STS2 PDU left side distribution ...
Страница 64: ...Installation Drawings 56 Figure 46 Control wiring 800A STS2 PDU right side distribution ...
Страница 65: ...Installation Drawings 57 Figure 47 Control connection location 250A STS2 PDU ...
Страница 66: ...Installation Drawings 58 Figure 48 Control connection location 400 800A STS2 PDU ...
Страница 67: ...Installation Drawings 59 Figure 49 Control location drawing conduit box top entry 400 600A STS2 PDU ...
Страница 68: ...Installation Drawings 60 Figure 50 Control wiring for the programmable relay board option ...
Страница 69: ...Installation Drawings 61 Figure 51 Control wiring for the input contact isolator board option ...
Страница 70: ...Installation Drawings 62 Figure 52 Control wiring for comms board ...
Страница 71: ...Installation Drawings 63 Figure 53 Control wiring for the internal modem option ...
Страница 72: ...Installation Drawings 64 Figure 54 Control wiring for the Network Interface Card NIC option ...
Страница 73: ...Installation Drawings 65 Figure 55 Control wiring for the RS 232 Port ...
Страница 74: ...Installation Drawings 66 Figure 56 Control wiring for remote source selection option ...
Страница 75: ...Installation Drawings 67 Figure 57 Color LCD touch screen display ...
Страница 155: ......