PRE-INSTALLATION STEPS

The appliance is shipped with all gas controls 

and components installed and pre-wired. 

Before installing the appliance, follow these 

steps:

1. Remove the shipping carton. 

2.  Remove the shipping pad, exposing the front 

glass door.

3. Open the two spring latches securing the 

glass door (under the firebox floor). Remove 

the door by tilting it outward at the bottom 

and lifting it up. Set the door aside, taking 

care to protect it from inadvertent damage. 

See Removing The Glass Enclosure Panel 

on

 Page 32

.

5. Remove the log set from the firebox. 

Handle 

logs carefully to prevent breakage.

6.  Remove the embers and volcanic stone from 

the control compartment.

dETAILEd INSTALLATION STEPS
Step 1. FRAMING

Frame the appliance as illustrated in 

Figures 

12 and 13 

on

 Pages 11 and 12 

(

Figure 13

 

applies to corner framing installations only). 

All framing details must allow for a minimum 

clearance to combustible framing members as 

shown in 

Table 5 on Page 8

.

If the appliance is to be elevated above floor level, 

a solid continuous platform must be constructed 

below the appliance.
Headers may be in direct contact with the 

appliance top standoff spacers 

when they are 

bent up vertically

, maintaining the 3" clearance 

to the fireplace top, 

but must not be supported 

by them or notched to fit around them

. All 

construction above the appliance must be 

self-supporting.

 

DO NOT use the appliance 

for structural support.

Secure the fireplace to the side framing members 

using the unit’s nailing flanges  -  one top and 

bottom on each side of the fireplace front. See 

Figure 11. 

Use 8d nails or their equivalent.

TYPICAL INSTALLATION SEQUENCE

The typical sequence of installation is outlined 

below; however, each installation is unique and 

may result in variations to the steps described. 

See the pages referenced in the following steps 

for detailed procedures.

Step 1. FRAMING 

(

Page  10

): 

Construct the 

appliance framing. Position the appliance within 

the framing and secure with nailing brackets. 

IMPORTANT! Bend up the appropriate header 

spacing standoffs for the drywall/finish 

material thickness to be used

 (see 

Figure 11

)

Bend up the outer pair for 1/2" materials and 

the inner pair for 5/8" materials.

Bend out the appropriate nailing flanges for 

the drywall/finish material to be used. Nailing 

flanges are provided for flush framing, 1/2" and 

5/8" framing depths (

see 

Figure 11

)

.

Step 2. ROUTING GAS LINE 

(

Page 12

):

 Route 

gas supply line to appliance location.

Step 3. PREPARING APPLIANCE VENT 

COLLAR 

(MPD35/40/45 models with combined top/rear 

vent) 

(

Page 13

).

Step 4. INSTALLING VENT SYSTEM

 

(

Page 13

):

 

Install the vent system and exterior termination. 

Step 5. FIELd WIRING 

(

Page 25

).

 

a. 

Millivolt Appliances - Install the operating 

control switch (not factory provided). If 

installing the optional forced air circulating 

blower, bring in electrical service line.

b.

 Electronic Appliances - Field wire and 

install operating control switch.

Step 6. WIRING - OPTIONAL FORCEd AIR 

BLOWER KIT

 

(

Page 26

)

.

Step 7. CONNECTING GAS LINE

 

(

Page 26

):

 

Make connection to gas supply.

Step 8. VERIFYING APPLIANCE OPERATION

 

(

Page 27

)

.

Step 9. INSTALL VOLCANIC STONE, GLOWING 

EMBERS, ANd LOGS 

(

Page 28

)

Step 10. INSTALLING GLASS dOOR 

ASSEMBLY 

(

Page 32

)

.

Step 11. BURNER AdJUSTMENTS 

(

Page 

32

): 

Adjust burner to ensure proper flame 

appearance.

Step 12. HOOd INSTALLATION

 

(

Page 34

)

Step 13. ATTACHING SAFETY-IN-OPERATION 

WARNINGS

 

(

Page 35

)

.

IMPORTANT!

Bend up the appropriate header spacing top 

standoffs before installing the fireplace.

Figure 11 - Unit Secured to Framing by 

Nailing Flange

NOTE: The nailing flanges, combustible members, 

and screw heads in areas directly adjacent to 

the nailing flanges are EXEMPT from the 1/2" 

clearance to combustible requirements for the 

firebox outer wrapper.
Combustible framing may be in direct contact with 

the nailing flanges and may be located closer than 

1/2" from screw heads and the firebox wrapper in 

areas adjacent to the nailing flanges. 
Frame the opening to the exact dimensions 

specified in the framing details in this manual.

Side

Framing

Unit Nailing Flange

(No clearance to 

combustible framing 

is required)

Header Spacing Top Standoffs

(two pairs on front edge of firebox top)

Lift up outer pair for

1/2” finish materials

Lift up inner pair for

5/8” finish materials

Содержание MPD35CNE

Страница 1: ...fire or explosion may result causing property damage personal injury or death WARNING AVERTISSEMENT AVISO HOT GLASS WILL CAUSE BURNS DO NOT TOUCH GLASS UNTIL COOLED NEVER ALLOW CHILDREN TO TOUCH GLAS...

Страница 2: ...cal Installation Sequence 9 Detailed Installation Steps 9 Step 1 Framing 9 Fireplace and Framing Specifications 10 Step 2 Routing Gas Line 11 Step 3 Preparing Appliance Vent Collar 12 Step 4 Installin...

Страница 3: ...is appliance can cause serious injury or death from fire burns explosion or carbon monoxide poisoning WARNING Failure to position the parts in accordance with these diagrams or failure to use only par...

Страница 4: ...55 0 052 19L52 MPD40 38 0 102 99K76 0 062 21L01 MPD45 37 0 104 24M10 52 0 0635 37G00 Table 4 Standard size installed at factory Part Cat Number REQUIREMENTS FOR THE COMMONWEALTHOFMASSACHUSETTS These f...

Страница 5: ...the appliance Cold Climate Insulation For cold climate installations seal all cracks around your appliance with noncombustible material and wherever cold air could enter the room It is especially imp...

Страница 6: ...ents Above Flat Or Sloped Roofs Ref NFPA 54 ANSI Z223 1 Roof Pitch H ft H m Flat 6 12 1 0 0 3 6 12 7 12 1 25 0 38 7 12 8 12 1 5 0 46 8 12 9 12 2 0 0 61 9 12 10 12 2 5 0 76 10 12 11 12 3 25 0 99 11 12...

Страница 7: ...er 5 12 7 cm 5 12 7 cm G Clearance to inside corner 2 5 08cm minimum SV4 5HT 2 6 15 2cm minimum SV4 5HTSS 2 5 08cm minimum SV4 5HT 2 6 15 2cm minimum SV4 5HTSS H Clearancetoeachinsideofcenterlineexten...

Страница 8: ...ve to conform to standard hearth extension installation requirements Shelf Height To provide for the lowest possible shelf surface use the alternate rear vent outlet the venting attached to the top ve...

Страница 9: ...the framing and secure with nailing brackets IMPORTANT Bend up the appropriate header spacing standoffs for the drywall finish material thickness to be used see Figure 11 Bend up the outer pair for 1...

Страница 10: ...lectrical Inlet Knockout requiring a Field Provided Junction Box either side E B D C Front View 3 76 A Header Spacing Top Standoffs Vertical Venting through the Ceiling Frame ceiling opening Use a plu...

Страница 11: ...aming 6 1 2 152 mm Pipe Coupling Recommended NOTE Rear Vent Applications in Corner Installations The horizontal vent length from a to b must not exceed 28 inches 711 mm MPDT33 and MPDR33 Models Dimens...

Страница 12: ...ct Venting System Horizontal or Vertical Withtheappliancesecuredinframing determine ventroutingandidentifytheexteriortermination location The following sections describe vertical roof and horizontal e...

Страница 13: ...4 1 1 0 0 5 0 6 3 8 1 5 2 5 1 0 1 0 5 0 6 6 8 1 5 5 1 0 0 0 0 4 4 5 0 9 1 5 7 8 5 1 1 0 0 0 4 5 5 6 9 1 5 7 3 6 1 0 1 0 0 4 5 5 5 0 2 5 2 1 7 1 0 1 1 5 0 7 7 0 2 5 2 7 1 0 0 0 6 0 6 5 1 1 2 5 2 6 7 1...

Страница 14: ...e radial alignment until the four locking dimples are aligned with the inlet of the four inclined channels on the collar refer to Figure 21 Push the vent component againstthecollaruntilitfullyengages...

Страница 15: ...llar section to align with the required direction of the next vent run element Twist elbow sections in a clockwise direction only so as to avoid the possiblity of unlocking anyofthepreviouslyconnected...

Страница 16: ...ou are allowed 2 feet of H horizontal run up to a maximum horizontal run of 8 feet Example If 8 feet of H horizontal vent run is needed then 4 feet minimum V vertical vent will be required TABLE A H M...

Страница 17: ...6 096 4 1 219 H H1 20 feet 6 096 m Max V V1 H H1 40 ft 12 192 m Max meters meters Example If 20 feet of H horizontal vent run is needed then 4 feet minimum of V vertical vent will be required This tab...

Страница 18: ...al both the inner and outer pipe elements with the same procedure Sealant and securing screws are not required NOTE An elbow may also be attached to the appliance collar Attach in the same manner as y...

Страница 19: ...4 32 mm as shown in Figure 34 SVHRK Snorkel Cap The snorkel cap is designed to be fitted into a basement window box The SVHRK cap is for use with flex vent The vertical distance between the inlet and...

Страница 20: ...owingwallthicknessrange when using SV4 5HT 2 termination kit HORIZONTAL Vent Figures Tables NOTE Secure Vent components rigid vent pipe and terminal are shown in the figures Secure Flex components fle...

Страница 21: ...of H horizontal vent run is needed then 4 feet minimum of V vertical vent will be required This table shows a 1 V to 5 H ratio For every 1 foot of V vertical you are allowed 5 feet of H horizontal run...

Страница 22: ...al rise except where an elbow is the only vertical component in the system See Figure 36 V Minimum feet feet 5 1 524 Elbow Only 5 1 524 1 0 305 10 3 048 2 0 610 15 4 572 3 0 914 20 6 096 4 1 219 meter...

Страница 23: ...No 10K81 to the inner adaptor collar approximately 1 2 inch from the end 3 Pull and extend the inner flexible vent pipe 4 Slide the inner flex pipe over the adaptor collar Ensure the flexible vent pip...

Страница 24: ...t of 2 conductor wire supplied with the unit NOTE The supplied 15 feet of 2 conductor wire has one end of each conductor connected to the gas valve circuit and the other end of each conductor placed l...

Страница 25: ...eplace The millivolt control valve has a 3 8 10mm NPT thread inlet port The electronic control valve has a 1 2 13 mm NPT thread inlet port and is fitted with a 1 2 x 3 8 13 mm x 10 mm NPT fitting Secu...

Страница 26: ...onovertime A Light the appliance refer to the lighting instructionslabelinthecontrolcompartment or in the Care and Operation Instructions manual B Brush all joints and connections with the gas leak te...

Страница 27: ...pli ances to Figure 54 for MPD35 Series appli ancesandtoFigure55forMPD40andMPD45 Series appliances WARNING DO NOT attempt to install the logs until the appliance instal lationhasbeencompleted the gas...

Страница 28: ...firebox with the log s notches directly over the brackets Position the right log log no 3 by inserting the pin from the rear log into the hole on its upper end Place the left log and then the smaller...

Страница 29: ...the order shown Position the rear log on the brackets at the rear of the firebox with the log s notches directly over the brackets Position the right log log no 3 by inserting the pin from the rear l...

Страница 30: ...ividual logs as shown below Logs should be placed in the order shown Position the center log on the burner first then place the glowing embers as shown in Figure 52 Place the rear log both the right a...

Страница 31: ...t appear sooty The following chart is provided to aid you in achieving the correct air shutter adjustment for your installation Figure 56 Removing the Glass Enclosure Panel see Figure 56 Remove the to...

Страница 32: ...ireplace rod located in the lower control area Position the air shutter to the factory setting as shown in the table in Figure 60 2 Light appliance follow lighting procedure on lighting label in contr...

Страница 33: ...bustible material may touch top of appliance Combustible materials NOT allowed below this point on face of appliance Header Spacing Top Standoff Top of Appliance Top of Door Frame Hood must be install...

Страница 34: ...er la poussi re et les traces de graisse ou d huile Collez l tiquette sur la surface de la plaque de l interrupteur mural qui contr le le foyer Figure A ou du thermostat mural Figure B Choisissez la l...

Страница 35: ...6 SV4 5HF 10 Firestop Spacer Hori zontal rigid 3 1 1 spac ing 10 Pack H2247 SV4 5VF 10 Firestop Spacer Verti cal rigid 1 1 1 spac ing 10 Pack 96K92 SV4 5SP Support Plate Installation Accessories Liste...

Страница 36: ...T48SS Small Square Termination for flex with 48 1219 mm of compressed flex vent Ref Instr 750204M 94L09 SF HTSS Horizontal Small Square Termination for flex without flex vent Ref Instr 750204M INSTALL...

Страница 37: ...pin located at the door s left side to the right until it disengages from the left corner post hole Pull the control compartment door diagonally to the left away from the fireplace Step 3 Remove the...

Страница 38: ...crews previously removed Step 12 Reinstall the baffle with the two baffle securing screws Step 13 Reassemble the remaining compo nents by reversing the procedures outlined in the Steps 1 5 Step 14 Att...