UAB KOMFOVENT we reserve the right to make changes without prior notice
MOU_22-10
17
Flare nut
Cap
Valve stem
Valve body
Fig. 6.2
9. Watch the Pressure Gauge for one minute to make sure that there is no change in pressure. The Pres-
sure Gauge should read slightly higher than atmospheric pressure.
10. Remove the charge hose from the service port.
11. Using hexagonal wrench, fully open both the high pressure and low pressure valves.
OPEN VALVE STEMS GENTLY
When opening valve stems, turn the hexagonal wrench until it hits against the stopper.
DO NOT try to force the valve to open further.
12. Tighten valve caps by hand, then tighten it using the proper tool.
6.2. Note On Adding Refrigerant
•
Refrigerant charging must be performed after wiring, vacuuming and the leak test.
•
DO NOT exceed the maximum allowable quantity of refrigerant or overcharge the system. Doing so
can damage or impact the unit’s function.
•
Charging with unsuitable substances may cause explosions or accidents. Ensure that the appropri-
ate refrigerant is used.
•
Refrigerant containers must be opened slowly. Always use protective gear when charging the sys-
tem.
•
DO NOT mix refrigerants types.
Some systems require additional charging depending on pipe lengths L (m).
Pipe diameter, mm
Ø 6,35
Ø 9,52
Ø 12,7
Ø 15,9
Additional refrigerant volume, g
15×(L-5)
30×(L-5)
110x(L-7,5)
170x(L-7,5)
The standard pipe length varies according to local regulations.