Kiefer Klimatechnik GmbH
www.kieferklima.de
INDUSAIL SONIC active acoustic sail system
Technical modifications reserved
- E1909_08/21
PART II-12
INSTALLATION INFORMATION
It must be possible to isolate the units from the
power supply across all poles!
All work must be carried out in accordance with
national requirements and safety regulations.
Wiring, fusing and earthing of the fan must comply
with local regulations.
Working on live electrical equipment of the unit is
not permissible. Operating the unit when open or
dismantled is not permissible.
The mains connection is made on site according to the supplied wiring diagram and may only be carried out by
technical personnel.
Even after the unit has been properly installed, it must still be checked for various faults.
Requirements for commissioning:
P
The unit must be inspected to verify that it is correctly mounted on the ceiling. This includes checking all threaded
connections, such as threaded rods, nuts and locking rings. Threaded rods must not be damaged or soiled in any way.
P
The media connections must be securely fastened.
P
The connections must not exhibit any mechanical damage or leaks. The connections must be tested for leaks before
commissioning.
P
All electrical connections must be established based on the enclosed wiring diagram (PART II-11).
P
The filter cells are attached to the unit and do not exhibit any soiling or damage.
P
The mains voltage, control voltage and frequency must comply with the specifications on the type plate.
P
The starting voltage for the fan must be sufficient.
P
The discharge profile must not be blocked.
P
The unit as a whole must be installed horizontally.
P
The media connections must be laid in such a way as to be tension-free and sufficiently long.
P
The supply media must be available in sufficient quantities on site.
Water connection
The hoses and connections of the heat exchanger
must be checked for damage before connecting it
to the water network.
Work may only be carried out on water connections
when the unit is isolated from the power supply.
After proper connection and before water is
introduced, the connecting points must be tested
for leaks.
Note! Before water is routed into the unit, it is
essential to check the flexible water connection
hoses for a correct and tight fit.
Sharp-edged heat exchanger fins and housing
parts.
Installation test and commissioning
Risk from falling parts!
The threaded rods must be fitted securely. Nuts
and locking rings must be tightened firmly. The
threaded rods must not be bent or distorted in any
way.
The test run and operation are only permissible
following correct installation in compliance with all
safety regulations and installation information.