Base Unit Assembly
for Bench Type Fume Hoods
BASE UNITS
REAR FILLER
(optional- install
as required)
KEMSTRUTS
(install as required)
Screws
(4) required
one each corner
FACE FILLER
(optional- install
as required)
WOOD SHIM
(cut off flush with cabinet
when leveling is complete)
ADJUSTMENT BOLT
(accessible thru cabinet bottom
with straight blade screw driver)
PLUG BUTTONS
1 / "
3 4
1 / "
1 2
5 / "
3 4
20"
36 / "
1 2
42 / "
1 2
48 / "
1 2
9"
15"
21"
BASE
CABINET
Pipe Space
Rear W
all
FUME
HOOD
Floor
Worksurface
Detail 1
Fume Hood Base Cabinet
Location
Detail 2S
Steel base cabinets
are leveled using the
adjustment bolts located
in the cabinet base.
Detail 2W
Wood base cabinets are
leveled using wood or
plastic shims, available at
any lumber yard or home
center.
Preparation
1. Locate and mark hood and base cabinet locations making sure area is clear of
obstructions and debris. Be sure all conduit, duct work and service lines have been
run and are ready for final connections.
NOTICE
Kemstruts and other pipe or worksurface supports should be installed
before the base cabinets are moved into place.
2. Locate the high point of the floor within the area that the base cabinets will be installed.
Installation
3. Starting with the base cabinet on the highest point on the floor, move the first cabinet
into location as shown in Detail 1 and according to project drawings.
4. Using a four foot carpenters level, level the cabinet; side-to-side, front-to-back, and
diagonally. (see Detail 2S and 2W to the left for leveling methods)
NOTICE
Blocks or cleats may be used to fasten cabinets to floor or walls to insure
cabinets don’t move during installation.
5. Move the next cabinet into position and clamp it to the first cabinet, making sure that
the cabinet faces and tops are flush.
6. Level the cabinet, as in step 4.
7. Using four (4) screws, as listed below, fasten the two cabinets together at all four
corners of the end panels.
Use #8 x 1-1/4" Flat Head screws for wood cabinets.
Use #8 x 1/2" Truss Head Sheet Metal screws for steel cabinets.
(pilot holes must be drilled in the steel cabinets before driving screws)
8. Complete hood installation and all mechanical connections before installing any
required fillers or scribes.
NOTICE
It is recommended that the polyethylene liner be removed from Acid Storage
cabinets during installation to allow fastening to adjacent cabinets and ease
plumbing connections. Be sure to replace when installation is complete.
Installation Instructions
PLUG BUTTON
ADJUSTMENT BOLT
(accessible through cabinet bottom
use 1/4" socket driver)