Table 8: Site Preparation Checklist for SSR1300 Installation
(Continued)
Item or Task
Additional Information
Plan the rack location,
including required space
clearances.
"Clearance Requirements for Hardware Maintenance of SSR1300" on page 19
Secure the rack to the floor
and building structure.
Cables
•
Acquire cables and
connectors.
•
Review the maximum
distance allowed for each
cable. Choose the length
of cable based on the
distance between the
hardware components
being connected.
•
Plan the cable routing and
management.
SSR1300 Site Guidelines and Requirements
IN THIS SECTION
General Site Installation Guidelines | 17
Site Electrical Wiring Guidelines | 17
Environmental Requirements and Specifications for SSR1300 | 19
Clearance Requirements for Hardware Maintenance of SSR1300 | 19
16