Installation
WARNING!
Installation is exclusively to be undertaken by per-
sonnel who are authorised to do so. During instal-
lation, make sure that both supports touch the
ground at the same time when the landing gear is
lowered. Having different loads on the supports
leads to damage. Follow the specifications (e.g.
installation directive) supplied by the semi-trailer
manufacturer and the installation instructions.
The manufacturer will not accept any warranty
claims if installation is carried out incorrectly.
The electrical connection (terminal 15 or 30) must
be made via a fuse on the tractor unit or semi-
trailer.
The electrical connection (terminal 31) must be at
an earth post provided by the manufacturer of the
semi-trailer.
Material required
28 x M16 hexagon screws (8.8)
The length of the bolts must be selected according to the
vehicle frame (if the standard console with the control ele-
ments is to be bolted onto the landing gear, these bolts must
be selected 20 mm longer than the screw connection without
standard console)
28 x self-locking hexagon nuts M16 (8)
28 x washers
Any additional fastening material required when using the
universal bracket for the control elements
Installation material such as cable ties, cable clamps, protec-
tive tubes, etc.