background image

ECH EVAPORATIVE CONDENSERS

OPERATION

140.910-IOM (DEC 13)

Page 12

  If  white  deposits  form  on  galvanized  steel  surfaces  after 

the  pH  is  returned  to  normal  service  levels,  it  may  be 
necessary to repeat the passivation process.

NOTICE

Stainless steel cold water basins and basins protected by 
the TripleGuard™ Corrosion Protection System or Ther-
mosetting  Hybrid  Polymer  do  not  require  passivation. 
However, if the upper structure is galvanized steel, pas-
sivation is required.

BIOLOGICAL CONTROL

  The  warm,  oxygen  and  nutrient  rich  environment 

inside  evaporative  cooling  equipment  provides  an  ideal 
environment  conducive  to  the  growth  of  algae,  slime, 
and other micro-organisms. Uncontrolled, this can reduce 
heat transfer, promote corrosion, and promote the growth 
of  potentially  harmful  organisms  such  as  Legionella.  To 
avoid  biological  contamination  and  minimize  the  risk 
of  Legionella,  initiate  the  biocide  treatment  program  at 
start-up  and  continue  on  a  regular  basis  thereafter  in 
accordance with the treatment supplier’s instructions.

  Bleed/blowdown or chemical treatment used for corrosion 

and  scale  control  alone  is  not  adequate  for  control  of 
biological contamination.

  Introduce  solid  or  granular  biocides  through  a  chemical 

“pot” feeder installed in parallel with the system circulating 
pump. Diluted liquid biocides may be added directly to the 
cold water basin.

  If  ozone  water  treatment  is  used,  at  no  point  should 

concentrations exceed 0.5 ppm.

  Initial Start-up and Start-up Following a Shutdown Period:

 

1.  To  minimize  the  risk  of  biological  contamination 

during  a  shutdown  period  of  three  days  or  more,  it 
is  recommended  that  the  entire  system  (evaporative 
cooling  equipment,  system  piping,  heat  exchangers, 
etc.) be drained.

 

2.  To resume operation of a drained system and at initial 

start-up,  clean  all  debris  from  the  cold  water  basin 
and  fill  the  system  with  fresh  water.  Then  execute 
one of the following biocide treatment programs while 
operating the circulating pump and prior to operating 
the unit fans:

 

a.  Resume treatment with the biocide that was used 

prior  to  shutdown.  Then  run  the  pump  only  while 
maintaining  the  maximum  recommended  biocide 
residual for a sufficient duration (residual and time 
will vary with the biocide) as recommended by the 
water  treatment  supplier.  Start  the  fan  only  after 
this treatment period is completed.

 

b.  Check  the  pH  of  the  circulating  water  and,  if 

necessary, adjust it to 7.0 - 7.6 pH. Then, running 
the  pump  only,  treat  the  system  with  sodium 
hypochlorite to maintain a level of 4 to 5 mg/l (ppm) 
free  chlorine  (as  Cl2)  over  a  6  hour  period.  Test 
kits for measuring the free residual of chlorine are 
commercially available. Start the fan only after this 
treatment period is completed.

 

c.  When it is not practical to drain the system during 

shutdown periods, install a bypass line with shutoff 
valves to permit the recirculating water to circulate 
throughout  the  system,  including  the  unit  basin, 
while  bypassing  the  fill  section  of  the  evaporative 
cooling equipment (fans should remain off).

 

d.  Treat the system as per one of the above-described 

methods prior to restarting the unit.

Содержание Frick ECH

Страница 1: ...ECH D Evaporative Condensers Please check www jci com frick for the latest version of this publication THIS MANUAL CONTAINS RIGGING ASSEMBLY START UP AND MAINTENANCE INSTRUCTIONS READ THOROUGHLY BEFO...

Страница 2: ...if Extended Downtime is a Concern 21 INSTALLATION Rigging and Assembly Instructions ECH ech d Evaporative Condensers 4 Shipping 4 Check Unit Before Rigging 4 Anchoring 4 Rigging 5 Section Assembly of...

Страница 3: ...ift Eliminators Spray Water Distribution System Power Train Axial Fan s Single Side Air Inlet ECH Dual Air Inlet ECH D Suction Strainer Spray Riser Pipe Bleed Valve Spray Pump Access Door Spray Pump M...

Страница 4: ...pe required to assemble sections or component parts are furnished by Frick and are shipped with the unit A checklist inside the envelope attached to the side of the unit marked Contractor s Installati...

Страница 5: ...tance between the spreader bar attachment points Figure 1 Two Section Units Figure 2 Plenum and Coil Sections Figure 3 Lower Section Two Section Units Four Section Units Model Number Section H W1 W2 E...

Страница 6: ...ler tape on the edge flange as shown in Figure 5 For multiple cell installations remove tie down plates from plenum and coil sections prior to setting sections Using drift pins in the bolt holes provi...

Страница 7: ...ith bolt hole at one corner and following down the flange Screw in place using the self tapping screws or bolts supplied with the unit to ensure leak free operation Figure 7 Assembly of Two Section Un...

Страница 8: ...for more details WARNING Do not perform any service on or near the fans motors drives or inside the unit without first ensuring that the fans and the pumps are disconnected and locked out NOTICE 1 Re...

Страница 9: ...in strainer and re install Cover the fan discharge opening to keep out dirt and debris Lubricate the fan shaft bearings motor base and motor base adjusting screw Close the shutoff valve in the makeup...

Страница 10: ...ambient temperature is below freezing Contact your local Frick Representative for guidelines on the installation of an emergency coil drain system Further protection against coil freeze up is possibl...

Страница 11: ...mall portion of the recirculating water to a drain is used to control the concentration of dissolved solids On rare occasions this may be adequate to control scale and corrosion More often however che...

Страница 12: ...Start up and Start up Following a Shutdown Period 1 To minimize the risk of biological contamination during a shutdown period of three days or more it is recommended that the entire system evaporativ...

Страница 13: ...ingle speed fan motors and drive assemblies One drive assembly is sized for full speed and load and the other is sized for approximately 2 3 speed and consumes only 1 3 the design horsepower The Senti...

Страница 14: ...belt deflects be tween 1 4 and 3 8 as shown in Figures 12a and 12b Belt tension adjustment if required 1 Loosen the lock nut on the motor base adjusting screw 2 Turn the motor base adjusting screw cl...

Страница 15: ...th the unit idle Add oil if level is below the oil level sight glass The standard oil provided is mineral oil Synthetic lubricants are also available as an option see Table 5 Refer to Table 6 for norm...

Страница 16: ...ties Service Oil Citgo Pacemaker 220 Conoco Hydroclear Multipurpose R O Oil 220 Exxon Teresstic 220 GulfOil Harmony 220 MobilOil DTE Oil BB Pennzoil Pennzbell TO 220 Philips Petroleum Magnus 220 Shell...

Страница 17: ...nal Start up Purge both bearings with new grease prior to start up 3 Operation Purge bearings every 2 000 hours of operation or once every 3 months whichever occurs first 4 Extended Shutdown Purge bea...

Страница 18: ...ent accumulations of scale corrosion sludge or biological growth which could interfere with the electrical circuit The water level is maintained at the recommended operating level regardless of the sy...

Страница 19: ...ontrol of the water quality is being maintained Bleed Line Calculations Bleed rate is determined by the fol lowing formula Bleed Rate B E n 1 Where B Bleed Rate GPM E Evaporation Rate GPM Q GPM x R F...

Страница 20: ...se adjusting screw X X X Check and lubricate optional gear drive See gear drive section for detailed instructions and schedule Check drive alignment X Check motor voltage and current X X X Clean fan m...

Страница 21: ...inventory of commonly used parts Even with this fast delivery capability it is still recommended that certain essential emergency repair parts be maintained in your local inventory to minimize any po...

Страница 22: ...ech Evaporative Condensers notes 140 910 IOM DEC 13 Page 22...

Страница 23: ...ech Evaporative Condensers notes 140 910 IOM DEC 13 Page 23...

Страница 24: ...Page 24 Johnson Controls 100 CV Avenue Waynesboro PA 17268 1206 USA Phone 717 762 2121 FAX 717 762 8624 www jci com frick Form 140 910 IOM 2013 12 Supersedes 140 910 IOM 2009 11 Subject to change with...

Отзывы: