Commissioning
Switch Unit ON / OFF (By Controller)
1.
With controller Home screen displayed, Press PRG button to go Main Menu screen and select “A. On/Off Unit”
2.
Press ENTER button. Screen A01 is displayed.
3.
Press ENTER button to move cursor from home position to SWITCH OFF value. Switch Unit ON by using UP/DOWN
arrows. Press ENTER button to confirm.
4.
Press ESC button repeatedly to return to Home Screen. This should now show ON by KEY at the bottom of the screen.
5.
The unit will start up following a short delay (assuming all conditions for compressor start
Switch Unit ON / OFF (By Controller)
displayed, Press PRG button to go Main Menu screen and select “A. On/Off Unit”
Press ENTER button. Screen A01 is displayed.
Press ENTER button to move cursor from home position to SWITCH OFF value. Switch Unit ON by using UP/DOWN
ENTER button to confirm.
Press ESC button repeatedly to return to Home Screen. This should now show ON by KEY at the bottom of the screen.
The unit will start up following a short delay (assuming all conditions for compressor start-
Page 22
displayed, Press PRG button to go Main Menu screen and select “A. On/Off Unit”
Press ENTER button to move cursor from home position to SWITCH OFF value. Switch Unit ON by using UP/DOWN
Press ESC button repeatedly to return to Home Screen. This should now show ON by KEY at the bottom of the screen.
-up are met).
Содержание JEHSD-0400-B3-M-3
Страница 31: ...Issue 01 08 2020 Page 31 Dimensional Drawings JEHSD 0400 B3 M 3 JEHSD 0600 B3 M 3 JEHSD 0800 B4 M 3 ...
Страница 32: ...Issue 01 08 2020 Page 32 Electrical Wiring Diagram JEHSD 0400 B3 M 3 JEHSD 0600 B3 M 3 ...
Страница 33: ...Issue 01 08 2020 Page 33 Electrical Wiring Diagram JEHSD 0800 B4 M 3 ...
Страница 39: ...Issue 01 08 2020 Page 39 Technical Information Small Version Controller ...
Страница 41: ...Issue 01 08 2020 Page 41 Certification ...
Страница 42: ...Issue 01 08 2020 Page 42 Certification ...
Страница 43: ...Issue 01 08 2020 Page 43 Certification ...