Operation and Maintenance Instructions
Envistar Top 04-21
DSET.181201.00.EN
Continuous product development may give rise to specification changes without notice.
5.3 Commissioning
Envistar Top (code ATEM, ATER) and Envistar Top with integrated EcoCooler
(code ATCR) cooling unti are factory built units that are tested and documented
in the factory.
Commissioning of the unit must be carried out by competent personnel in ac-
cordance with the Commissioning Procedure:
• For Envistar Top (code ATEM, ATER), refer to
Commissioning Checklist for air
handling units
at
.
• For Envistar Top with integrated cooling unit (code ATCR), refer to
med EcoCooler Commissioing Procedure
at
The commissioning procedure applies to units that are supplied with control
equipment (code MX).
The validity of the product warranty is conditional on the system having been
correctly commissioned. Working on the cooling unit during the warranty period
without the approval of IV Produkt shall render the warranty void.
Prior to commissioning, the contractor must:
NB:
Wiring of connections and other electrical work may only be carried out
by a qualified electrician or by service personnel recommended by IV
Produkt.
1. Connect the unit to the power supply via a lockable safety switch.
2. Connect the heating/cooling coil, if relevant.
3. Connect the electrical quick-connectors between the unit parts, if relevant
(size 12,16 och 21).
4. Pressure and temperature sensor
5. Connect all ducts.
WARNING!
Rotating fan impeller. The unit must not be energised until all
ducts have been connected.
Follow the troubleshooting instructions in the troubleshooting chart before
contacting a service representative for servicing a unit under warranty. This will