58
Ingeteam Energy, S.A.
AAV2000IKI01
Installation manual
5.5.3. Synchronisation of electronic blocks in units connected to the same
inverter
All electronic blocks should be synchronised.
The inverter blocks have built-in synchronisation of the inverter blocks. If you wish, you may connect two units to a
single transformer, provided these are not setup in the master-slave configuration, in which case two separate wind-
ings would have to be used.
Master
Slave
To perform this synchronisation, turn the switch of a unit to position 18 and the other to 9, as shown in the figure. The
cards will also be connected via a fibre cable.
The configuration of PV array voltages should be the same.
MPPTs connected by TL inverters to the same transformer should have the same voltage settings.