Getting more than 50% difference in readings for fixed load calibration will mean that
subsequent re-work of the CAT5E cable terminations, along with ensuring the CT
clamp is positioned correctly on the Live incoming feed (as per section “Attaching
the External CT Clamp”)
In this event, installers are advised of the need for further calibration or rework to
reduce difference in readings.
At this stage there is also an option to skip calibration.
However, it should be noted
that if power variance is left above 50%, subsequent site visits may be required to
rectify, where post commissioning calibration is unable to bring this variance down.
Or if the customer opts into microgeneration/ curtailment in the future.
At any stage of the commissioning and calibration flow, where all best endeavours
have been made, there is an option to skip calibration.
Skip Calibration
38
38
Содержание 190105A101
Страница 1: ...1 Indra Pioneer Pioneer Installation Guide...
Страница 7: ...7...
Страница 18: ...Images of pig tailed mains cables into the charger 18...
Страница 33: ...33...
Страница 44: ...44...