background image

Concord CX - 

Installation

9

FOUNDATION

The boiler must stand on a non-combustible floor (i.e. concrete
or brick) which must be flat, level and of a suitable load bearing
capacity to support the weight of the boiler (when filled with
water) and any ancillary equipment.

If the boiler is mounted on a plinth then the dimensions must
exceed the plan area of the boiler by at least 75mm on each
side.

VENTILATION

Safe, efficient and trouble-free operation of conventionally flued
gas boilers is vitally dependent on the provision of an adequate
supply of fresh air to the room in which the appliance is
installed.  Ventilation by grilles communicating directly with the
outside air is required at both high and low levels. The minimum
free areas of these grilles must be according to the following
scale:

Table 5 - Ventilation Requirements

Total input

Position of air

Air vent areas (air

rating of boilers

vents

direct from outside)

Upto 2 MW

HIGH LEVEL

270 cm

2  

plus

2.25 cm

2

 per kW

in excess of 60 kW

 total rated input

Upto 2 MW

LOW LEVEL

540 cm

2   

plus

4.5 cm

2

 per kW

in excess of 60 kW

 total rated input

Position ventilation grilles to avoid the risk of accidental
obstruction by blockage or flooding.  If further guidance on
ventilation is required then consult BS.6644.

AIR SUPPLY BY MECHANICAL VENTILATION

The supply of air by mechanical means to a space housing the
boiler should be by mechanical inlet with natural or mechanical
extraction. Mechanical extract ventilation with natural inlet must
NOT be used.

Where a mechanical inlet and a mechanical extract system is
applied, the design ventilation flow rates should be as in Table 4
of BS.6644.

The requirements for air supply by mechanical ventilation are
given in BS.6644.

Note. 

For mechanical ventilation systems an automatic control

should be provided to cause safety shutdown or lockout of the
boiler(s) in the event of failure of air flow in either inlet or extract
fans.

IMPORTANT.

 

The use of an extractor fan in the same room as

the boiler (or in an adjacent, communicating room) can, in
certain conditions, adversely affect the safe operation of the
boiler.  Where such a fan is already fitted (or if it is intended to fit
an extractor fan after installation of the appliance) the advice of
the Gas Region should be obtained.

Tests for spillage of products from the draught diverter when the
extractor fan is running and all doors and windows are shut
should be carried out after installation.  If spillage is detected,
the area of permanent ventilation must be increased.

CHIMNEY SYSTEM

To ensure the safe and satisfactory operation of the boiler the
chimney system (which may be common or individual,  in the
case of twin or multiple boiler installations) must be capable of
the complete evacuation of combustion products at all times.
The effective height of the chimney terminal(s) above the boiler
outlet(s) must ensure sufficient buoyancy to overcome the
resistance of the bends, tees and runs of the flue pipe involved
and shall terminate in a down draught free zone.  The number of
bends and lengths of horizontal flue pipe used should be kept to
a minimum in order to reduce gas flow resistance.

Compliance with the recommendations made in BS.6644, British
Gas publication IM 11 ‘Flues for Commercial and Industrial Gas
Fired Boilers and Air Heaters’ and the’ Third Edition of the 1956
Clean Air Act Memorandum’ should be strictly observed where
applicable.

The chimney design should avoid the formation of excessive
quantities of condensate.  For this reason it is recommended
that all chimneys are insulated and lined.  In the case of brick or
similar structures a stainless steel rigid or flexible flue liner
(grade 304/316) may be used in conjunction with a 50 mm
(minimum) thick layer of vemiculite or perlite granules between
the liner and the inner skin of the chimney body.  Liners should
be sealed at both top and  bottom.

As the 

Concord CX range

 of boilers is supplied complete with

an integral draught diverter, a diverter MUST 

NOT 

be fitted

within the chimney system.

Drainage points positioned at the bottom of all vertical chimney
sections should be provided.  Drain pipes should be no less
than 25 mm  I.D., manufactured from acid condensate resistant
material such as stainless steel and be positioned so that pipe
runs and discharge points are not subject to the effects of frost
and that flue gases cannot leak into the boiler room.

Care should be taken to ensure the specification of the chimney
is suitable for the application by reference to the manufacturers
literature.  

Caradon Plumbing Limited

 can offer advice on the

design of suitable chimney  systems.

GAS SUPPLY

If there is any doubt regarding the capacity of the gas meter, the
available gas pressure, the adequacy of existing service pipes
or the size required for new service pipes then the advice of the
gas region should be requested.

Installation pipework should be fitted and tested for gas
soundness in accordance with BS. 6891;

IGE-UP-1  for small installations
IGE-UP-2  for large installations.

The local gas region must be consulted if it is necessary to
employ a gas pressure booster.

ELECTRICAL SUPPLY

WARNING. 

This appliance must be efficiently earthed.

A 230 V - 50 Hz mains supply is required, fused at 5 amps.

Wiring external to the appliance MUST be in accordance with
the I.E.E. (BS. 7671) Wiring Regulations and any local
regulations which apply.

For details of connections refer to Frame 14.

GENERAL

Содержание Concord CX40

Страница 1: ......

Страница 2: ...2 Concord CX Installation CAUTION To avoid the possibility of injury during the installation servicing or cleaning of this appliance care should be taken when handling edges of sheet steel components...

Страница 3: ...the law is complied with The Concord CX40 100 range of boilers has been tested and certified by British Gas to prEN656 for use with Natural gas only Multiple boiler installations The Concord CX range...

Страница 4: ...in BSP 2 x 2 at rear Return tappings Rc in BSP 2 x 2 at rear Maximum static head metres feet 45 7 150 Maximum pressure bar p s i 4 5 65 Gas inlet connection Rc in BSP 3 4 3 4 1 1 Minimum dynamic mbar...

Страница 5: ...auge kit In addition to the above control kit an optional pressure gauge is also available for the range of boilers Details for fitting are included with the pressure gauge Downdraught thermostat kit...

Страница 6: ...learance should be given at the rear of the boiler for connection of gas and water pipework Additional clearance is required for access at either end of the installation 2 CLEARANCES DIMENSIONS Boiler...

Страница 7: ...n will depend upon the particular characteristics of the system Pumping over of water into the expansion cistern must be avoided achieved either by provision of an adequate bypass circuit or by ensuri...

Страница 8: ...setting Other British Standards applicable to commercial sealed systems are BS 6880 Part 2 BS 1212 BS 6281 Part 1 BS 6282 Part 1 BS 6283 Part 4 Working pressure 4 5 bar maximum Particular reference s...

Страница 9: ...em which may be common or individual in the case of twin or multiple boiler installations must be capable of the complete evacuation of combustion products at all times The effective height of the chi...

Страница 10: ...ngs 5 End section 6 Gas cock 13 Section bolt 14 Distribution tube 15 Tie rods 16 Thermostat pocket 17 Spillage skirt 18 Flueway baffles 19 Gas pipe 7 Drain cock 8 NOx duct 9 Front plate 10 Burner mani...

Страница 11: ...g 2 BSP handling bars 9 Using the handling bars manoeuvre the boiler forwards on the packaging base and slide over collapsing base on to the floor Note Before manoeuvring the boiler into its final pos...

Страница 12: ...er lower rear connection using the gasket and M10 x 25mm screws and washers provided 3 Temporarily screw the 2 handling bars 2 pipe into the top tappings and manoeuvre the boiler into position 4 Compl...

Страница 13: ...e the flue connection 2 The boiler is designed to accept flues to BS 835 and should be sealed with an approved boiler putty 11 GAS CONNECTION 1 Connect the gas supply to the gas inlet pipe at the rear...

Страница 14: ...e temperature sensing probe through the cable clips provided and into the thermostat pocket adjacent to the flow connection Fit the plastic Heyco bush over the sensor lead at the line shown and insert...

Страница 15: ...cal supply such as a double pole switch having a 3mm 1 8 contact separation in both poles or a plug and socket serving only the boiler and system controls The means of isolation must be accessible to...

Страница 16: ...atisfy the conditions in the foregoing paragraph If not all zones can do this then consider other means of control detailed on other sheets Normal operation When any thermostat is satisfied while othe...

Страница 17: ...ls for heat its thermostat will open Zone 1 valve via the normally open contacts of the relay IMPORTANT Terminal L2 may control the appropriate pump s directly provided that the total running or start...

Страница 18: ...groove in square head in line with the pipe 5 Press the overheat thermostat reset button 2 6 Push in and retain fully depressed the grey button 4 on the gas control 5 At the same time repeatedly push...

Страница 19: ...ilitate speedy approximate adjustment of the gas rate After setting to the indicated pressure allow the boiler to operate for about 15 minutes to stabilise then check the gas rate by reference to a wa...

Страница 20: ...the minimum flow rate given in Table 4 when that part of the system intended to be used for dissipation of residual heat only is in operation 26 HANDING OVER ROUTINE OPERATION Full instructions coveri...

Страница 21: ...sitioned 3 The ignition electrode and lead are clean undamaged secure and correctly dimensioned Refer to diagram in Frame 28 4 The thermocouple tip is NOT burned or cracked 5 The thermocouple terminal...

Страница 22: ...front plate fits behind the burner retaining returns when it is replaced Refit the flue baffles cleanout cover NOx duct casing top panel and casing door PILOT BURNER Check that 1 The pilot flame cover...

Страница 23: ...ble in reverse order checking that the spark gap is as shown in Frame 28 SERVICING SERVICING To facilitate the replacement of components remove and replace the lower front panel NOx duct and the burne...

Страница 24: ...ge connection 7 Test for gas soundness 35 MAIN BURNER 1 Remove the NOx duct and burner front plate as previously described in Frame 27 2 Both left and right hand burners can be removed by sliding each...

Страница 25: ...in injector 3 off 9 Gas inlet manifold 10 Pilot gas pipe 11 Overheat thermostat piezo generator mounting bracket 12 O ring seal 13 Thermocouple 14 Spark electrode 15 Pilot draught shield 16 Pilot burn...

Страница 26: ...ing in the clips provided Detail of Printed Circuit Board Support SERVICING 40 CONTROL BOX Basic Boiler Exploded View 41 CONTROL SENSOR 1 Remove the lower front panel Refer to Frame 27 2 Remove the se...

Страница 27: ...OMBUSTION CHAMBER INSULATION REPLACEMENT The insulation boards used in the combustion chambers of these products contain man made fibres refractory fillers organic and inorganic binders and as such ar...

Страница 28: ...mocouple and pilot gas pipe connections at the gas valve must be removed and the igniter lead pulled off at the igniter 4 The centre burner may now be removed by pushing it back to clear the injector...

Страница 29: ...oming apart 8 Repeat the above procedure for all of the remaining sections until the assembly is complete 9 Fit the 4 tie rods through the holes in the sides of the end sections and fit a flat steel w...

Страница 30: ...ical checks to be carried out during a fault finding procedure On completion of any service fault finding task which has required the breaking and remaking of electrical connections Check that the gap...

Страница 31: ...ling for heat if necessary withdraw the sensor from the thermostat pocket NO NO 49 PILOT LIT BUT NO MAINS GAS NO NO Have you confirmed that the system controls are calling for heat YES FAULT FINDING Y...

Страница 32: ...racket VERNITRON 60080 002 1 003 939 32 Ignition electrode and H T lead assembly VERNITRON 1 130 947 33 Thermocouple HONEYWELL Q 309 A 2762 1200mm long 1 002 937 34 Thermocouple interrupter lead assem...

Страница 33: ...1 111 651 CX 70 1 111 652 CX 80 1 111 652 CX 90 100 1 111 653 50 Jacket top panel white stove enamel CX 40 1 111 293 CX 50 1 111 294 CX 60 1 111 295 CX 70 1 111 296 CX 80 1 111 297 CX 90 100 1 111 298...

Страница 34: ...ursues a policy of continuing improvement in the design and performance of its products The right is therefore reserved to vary specification without notice Technical Training The Caradon Plumbing Lim...

Страница 35: ...giving away a free boiler for the five best ideas every year to be selected by our Technical Director Please complete this form using extra sheets if required and post it or fax it to us on 01482 498...

Страница 36: ...lease arrange for me to join an Ideal factory tour Range guides required The Ideal Guide a specifier s and installer s introduction to the Ideal domestic boiler range The Ideal Householders Guide to a...

Отзывы: