Table 7. Clustered gateway installation checklist (continued)
U
Task
Description
Where to find information
h
8–5
Turn the system over to the customer. If
replication is being used, advise the customer
that it is their responsibility to create and
configure the replication grid.
N/A
Installing the server
Use this procedure to install the server.
About this task
Important:
The customer is responsible for ensuring that any recommended
hardware components that were not included in the purchase of the TS7650G, such
as disk controllers and disk expansion module, are installed in a frame, cabled, and
fully configured; before server installation begins.
Procedure
1.
If any components installed in the server and/or disk storage frames are
powered-on, have the customer suspend all I/O activity, and then power-off
the components.
2.
Physically install the server (or both servers, in a clustered gateway
configuration) into the server frame.
3.
Once physical installation and labeling is complete, go to “Installing the TSSC
and Ethernet switch.”
Installing the TSSC and Ethernet switch
Use this procedure to install the TSSC and any related components.
Before you begin
Important:
If the customer purchased a TSSC, you are required to install it and its
related components, along with the other gateway hardware. Failure to do so will
prevent the use of Call Home or IBM remote support.
Procedure
1.
Physically install the TSSC and its related components into the server frame.
Use the documentation provided with the TSSC for installation instructions.
Attention:
The recommended location for installing the TSSC is in EIA Unit
18. Use EIA holes 52, 53, and 54 for the installation of the rail assembly for the
TSSC. The rail pins should extend through holes 52 and 53 at the front and rear
of the frame. See Figure 8 on page 31 for the recommended mounting locations
for the TSSC.
The KVM and TSSC switch should be mounted directly under the TSSC in EIA
Unit 17. Use EIA holes 49, 50, and 51 for the installation of the KVM rail
assembly. Mounting clips should be placed in holes 49 and 51 (EIA Unit 17) in
the front and rear of the frame. Use the rail assembly mounting position at the
rear of the frame to secure the TSSC network switch when added after the
KVM assembly is installed.
30
IBM System Storage TS7600 with ProtecTIER: Installation Roadmap Guide
|
Содержание System Storage TS7600 ProtecTIER Series
Страница 2: ......
Страница 7: ...Russia Electromagnetic Interference EMI Class A Statement 189 Index 191 Contents v ...
Страница 8: ...vi IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 10: ...viii IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 12: ...x IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 16: ...xiv IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 30: ...xxviii IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 38: ...xxxvi IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 44: ...6 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 46: ...8 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 54: ...16 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 89: ...Figure 20 Clustered TS7650G power cabling Chapter 4 Installing the TS7650G hardware 51 ...
Страница 120: ...82 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 148: ...110 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 150: ...112 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 156: ...118 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 172: ...134 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 192: ...154 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 198: ...160 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 210: ...172 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 220: ...182 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 228: ...190 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide ...
Страница 231: ......
Страница 232: ... Part Number 46X6052 Printed in USA or Mexico GC53 1154 09 1P P N 46X6052 ...