Start-up Checklist
Check
Tested efficiency of the appliance and made necessary adjustments by
combustion test and adjustment
.
□
Tested the low water cutoff function to check that the LWCO sensor is working. Refer to
"Testing the LWCO function" in the
Controller
manual.
□
Tested the high limit temperature function to check that the High limit temperature sensor
is working. Refer to "Testing the Hi-Limit cutoff temperature function" in the
Controller
manual.
□
6.2 Testing the ignition safety shutoff
To test the ignition system safety shutoff function:
1. With the boiler in operation, shut off the gas control valve directly outside the boiler case.
2. Ensure that the boiler has purged, attempted to re-light three times, has shut off and the
appropriate error information is displayed on the controller.
3. The error is displayed after testing the ignition safety shutoff.
4. To restart the boiler, reset the power or on the
touchscreen controller
tap
(Status)>
Clear Errors
>
Yes
.
6.3 Commissioning
The appliances are factory calibrated to operate with natural gas (or propane if desired) at sea
level. The gas-air ratio or zero-offset adjustment screw may need adjusting to attain optimum
combustion results. Note that only qualified technicians using properly functioning and calibrated
combustion analyzing equipment should perform a mixture adjustment.
68
Section: Boiler operation
Содержание SL 10-85 G3
Страница 8: ...Intentionally left empty ...
Страница 14: ...Intentionally left empty ...
Страница 66: ...Figure 49 Electric wiring connections 62 Section Installation ...
Страница 78: ...Intentionally left empty ...
Страница 92: ...Intentionally left empty ...
Страница 105: ...101 Appendices Wiring diagrams V 10 Controller electrical diagram Figure 52 Controller electrical diagram ...
Страница 106: ...Internal wiring diagram Figure 53 Internal wiring diagram 102 Section Appendices ...
Страница 107: ...Sequence of Operation Figure 54 Sequence of Operation 103 Sequence of Operation ...
Страница 109: ...105 Exploded views of boiler parts ...
Страница 114: ...110 Section Appendices ...
Страница 118: ...Item Description Part Quantity 200 Fan Coupler 250 749 P 347 1 205 Fan Coupler O ring 150 254 1 114 Section Appendices ...
Страница 122: ...Intentionally left empty ...