6 System Commissioning
Issue 01 (2020-02-14)
Copyright © Huawei Technologies Co., Ltd.
70
Put on insulation gloves before powering off the system.
Step 1
Turn off the single-phase power switch that controls the power supply from the remote
transformer station to the SACU.
Step 2
Turn off the three-phase power switch that controls the power supply from the remote
transformer station to the SACU.
If the SACU supports the access of one MBUS route, turn off the corresponding
three-phase power switch.
If the SACU supports the access of two MBUS routes, turn off the corresponding
three-phase power switches.
Step 3
Turn off the QF03 single-phase input switch in the SACU.
Step 4
Turn off the three-phase input switch in the SACU.
If the SACU supports the access of one MBUS route, turn off the FU01 switch.
If the SACU supports the access of two MBUS routes, turn off the FU01 and FU02
switches.
----End