5 Electrical Connections
Issue 01 (2020-02-14)
Copyright © Huawei Technologies Co., Ltd.
53
Connect a PE cable to the nearest ground point or the ground bar in the transformer
station.
To enhance the corrosion resistance of a ground terminal, you are advised to apply silica
gel or paint on it after connecting the ground cable.
Figure 5-5
Connecting a PE cable
5.4 Connecting the Communications Cables for the Fiber
Ring Network
Connecting the Optical Jumpers
Step 1
Obtain optical modules from the fitting bag for optical ring switching.
Step 2
Insert an optical module into the SFP1 or SFP2 port. If there are two modules, insert one into
each port.