Prerequisite
The metal pole is ready and the pole diameter stays within the range of 60 mm to 114 mm.
Procedure
Step 1
Determine the position of the mounting plate by referring to the engineering design and
3.1.2
Space Requirements of the RRU3804 and SRXU
.
NOTE
The upper fixture assembly should be 1,200 mm to 1,600 mm above the ground or rooftop.
Step 2
Mount the upper fixture assembly on the metal pole. Ensure that the four ends of the fixture
assembly are on the same plane, as shown in
Figure 3-12
.
Figure 3-12
Mounting the upper fixture assembly
Step 3
Use the level bar to check whether the four ends of the fixture assembly are on the same plane.
Use the tape measure to check whether the two pole fixtures are parallel.
NOTE
If the difference between L1 and L2, as shown in
Figure 3-13
, is beyond ±1 mm, the two pole fixtures are
not parallel.
RRU3804
User Guide
3 Installing RRU3804 and SRXU Hardware
Issue 01 (2007-11-29)
Huawei Technologies Proprietary
3-15
Содержание RRU3804
Страница 1: ...RRU3804 V100 User Guide Issue 01 Date 2007 11 29 Part Number 31018637 Huawei Technologies Proprietary ...
Страница 6: ......
Страница 12: ...Table 4 3 LEDs on the SRXU 4 3 Tables RRU3804 User Guide x Huawei Technologies Proprietary Issue 01 2007 11 29 ...
Страница 16: ......
Страница 30: ......
Страница 64: ......