Step 5
Clamp the new CIM to the fastener.
Step 6
Set the DIP switch for the CIM based on the recorded information.
Step 7
Reconnect cables to the CIM based on the cable labels.
Step 8
After installing the CIM, network the CIM and BIM. For details, see the description about
power-on commissioning in the
iBAT 2.0-CIM01C2 User Manual
.
----End
Follow-up Procedure
Dispose of the removed CIM that is confirmed faulty.
4.3.16 Removing a Camera SPD Module
Prerequisites
A spare camera SPD module of the same model is available and functional.
Context
An SPD module consists of an SLPU and a UFLP. The SLPU is a 19-inch wide and 1 U high
box-type device. Figure 4-60 shows the SLPU, and Figure 4-61 shows the UFLP panel.
Figure 4-60
SLPU appearance
Figure 4-61
UFLP panel
FE/GE0 and FE/GE1 at the INSIDE side;
connecting to monitoring devices outside the
pre-fab. module
FE/GE0 and FE/GE1 at the OUTSIDE side;
connecting to the LAN switch inside the
pre-fab. module
Impact on the System
None