INSPECTION ACTIVITIES
DATE LAST COMPLETED
PIPING
1
st
YEAR
2
nd
YEAR
3
rd
YEAR
4
th
YEAR*
Near boiler piping
Check boiler and system piping for any sign of leakage, make
sure they are properly supported.
Vent
Check condition of all vent pipes and joints.
Gas
Check Gas piping, test for leaks and signs of aging. Make sure
all pipes are properly supported.
SYSTEM
Visual
Do a full visual inspection of all system components.
Functional
Test all functions of the system (Heat, Safeties)
Temperatures
Verify safe settings on heater or Anti-Scald Valve
Temperatures
Verify programmed temperature settings
ELECTRICAL
Switch and Plug
Verify ON/OFF switch and convenience plug are functional.
Connections
Check wire connections. Make sure they are tight.
Smoke and CO
detector
Verify devices are installed and working properly. Change
batteries if necessary.
Circuit Breakers
Check to see that the circuit breaker is clearly labeled. Exercise
circuit breaker.
CHAMBER/BURNER
Combustion Chamber
Check burner tube and combustion chamber coils. Clean
according to maintenance section of manual. Vacuum
combustion chamber.
Spark Electrode
Clean. Set gap at ¼”.
Flame Probe
Clean. Check ionization in uA (d7 on status menu in Start-up
Procedures). Record high fire and low fire.
CONDENSATE
Neutralizer
Check condensate neutralizer. Replace if necessary.
Condensate hose
Disconnect condensate hose. Clean out dirt. Fill with water to
level of outlet and re-install. (NOTE: Verify the flow of
condensate, making sure that the hose is properly connected
during final inspection.)
GAS
Pressure
Measure incoming gas pressure (
3.5” to 14” W.C.)
Pressure Drop
Measure drop in pressure on light off (no more than 1” W.C.)
Check gas pipe for
leaks
Check piping for leaks. Verify that all are properly supported.
COMBUSTION
CO/CO2 Levels
Check CO and CO2 levels in Exhaust (See Start-up Procedures
for ranges). Record at high and low fire.
SAFETIES
ECO (Energy Cut Off)
Check continuity on Flue and Water ECO. Replace if corroded.
Water Pressure Switch
Check operation and for signs of leakage. Replace if corroded.
Thermistors
Check wiring. Verify through ohms reading.
FINAL INSPECTION
Check list
Verify that you have completed entire check list. WARNING:
FAILURE TO DO SO COULD RESULT IN SERIOUS INJURY
OR DEATH.
Homeowner
Review what you have done with the homeowner.
Table 20 -
*Continue annual maintenance beyond the 4
th
year as required.
Содержание 140M
Страница 12: ...12 LP 185 Rev 9 9 14 Figure 1 Dimensions T 50M T 80M 80M ...
Страница 13: ...13 LP 185 Rev 9 9 14 Figure 2 Dimensions 140M 199M 399M ...
Страница 48: ...48 LP 185 Rev 9 9 14 I DIAGRAMS FOR SIDEWALL VENTING Figure 25 Venting ...
Страница 49: ...49 LP 185 Rev 9 9 14 Figure 26 Sidewall Venting ...
Страница 50: ...50 LP 185 Rev 9 9 14 J DIAGRAMS FOR VERTICAL VENTING Figure 27 Vertical Venting ...
Страница 55: ...55 LP 185 Rev 9 9 14 Figure 29 ...
Страница 70: ...70 LP 185 Rev 9 9 14 Figure 31 ...
Страница 71: ...71 LP 185 Rev 9 9 14 Figure 32 ...
Страница 72: ...72 LP 185 Rev 9 9 14 Figure 33 ...
Страница 73: ...73 LP 185 Rev 9 9 14 Figure 34 ...
Страница 74: ...74 LP 185 Rev 9 9 14 Figure 35 ...
Страница 75: ...75 LP 185 Rev 9 9 14 Figure 36 ...
Страница 78: ...78 LP 185 Rev 9 9 14 ...
Страница 79: ...79 LP 185 Rev 9 9 14 ...
Страница 80: ...80 LP 185 Rev 9 9 14 MAINTENANCE NOTES ...