15.1 PIPING MATERIALS
1
Prepare locally-supplied copper pipes.
2
Select the appropriate pipe size according to the table below.
Unit: mm
Model
Gas Pipe
Liquid Pipe
RCD-0.8FSN3
RCD-1.0FSN3
RCD-1.5FSN3
RCD-2.0FSN3
Ø12.7
Ø6.35
RCD-2.5FSN3
RCD-3.0FSN3
RCD-4.0FSN3
RCD-5.0FSN3
RCD-6.0FSN3
Ø15.88
Ø9.52
3
Select clean copper pipes. Make sure there is no dust and
water inside. Use a pipe cutter when cutting the pipes, to
avoid a grind swarf generation. Do not use a saw or a grind
stone to cut pipes. Blow the inside of the pipes with nitrogen
or dry air, to remove any dust or foreign materials before
connecting pipes.
N O T E
5HIHUWRWKHWHFKQLFDOGRFXPHQWDWLRQRIWKHRXWGRRUXQLWIRUGHWDLORQ
DOORZDEOHSLSHOHQJWK
• Notice for Refrigerant Pipe Ends
Correct
Correct
Correct
Hole
In case of getting the pipe through a
hole in the wall
Do not place the pipe directly on
the ground.
Attach a cap or put a plastic bag
over the pipe end
Attach a cap or put a plastic bag
over the pipe end
Attach a cap or put a plastic bag
over the pipe end
Rain water can come in
In case of rain
Rubber band
Hole
Incorrect
Incorrect
Incorrect
Due to the change of the refrigerant oil, the refrigerant
cycle is more subject to foreign matters such as moisture,
R[LGH¿OPDQGIDW%HFDUHIXOWKDWPRLVWXUHGXVWRUGLIIHUHQW
refrigerant does not enter the refrigerant cycle during
LQVWDOODWLRQZRUN2WKHUZLVHVXFKSDUWVDVDQH[SDQVLRQ
valve might bite into foreign matters and so the operation will
be unavailable.
ENGLISH
REFRIGERANT PIPING WORK
PMML0416A rev.0 - 12/2015 - P5415720
21