COMMISSIONING

25

 Close the fill and drain valve - safety group (Fig. 19 Item 1) 
and the fill and drain valve - flow meter (Fig. 19 Item 2) and pressurise the pump 
slightly prior to filling the system. If an electric pump is being used follow the 
instructions with the pump.
Fully open the fill and drain valve on the safety group (Fig 19, item 1) and pump 
fluid into the system. Whilst pumping, open the flow meter drain valve (Fig 19, 
item 2) slightly to allow the air to vent out of the system.
When the pump is down to approximately 1 litre isolate the fill and drain valves. 
Vent the filling pump and refill with solar heat transfer fluid.
 Re-pressurise the filling pump and repeat the steps above until fluid is seen 
discharging from the drain valve on the flow meter. (Fig 19, item 2). Close the 
drain valve.
 Continue filling at the fill and drain valve on the safety group (Fig 19, item 1) until 
the system pressure reaches 2 bar.
At this point the circulation pump should be vented. If the system pressure drops, 
repressurise using the procedure above.
After venting the pump and checking that the system pressure is 2 bar, close the 
fill and drain valve on the safety group (Fig. 19 Item 1), and check the system for 
leaks.
Turn the left hand isolating valve (Fig 19, item 4) back 45° clockwise until the dot 
on the bezel is back at 12 o’clock.
 Turn the right hand isolating valve (Fig. 19 Item 5) back 90° clockwise until the dot 
on the bezel is back at 12 o’clock.
 Turn the slot of the adjusting screw (Fig. 19 Item 3) back to the horizontal position.

Commissioning of hydraulic station

Ensure the solar primary system is free from air
Switch on the power supply to the solar differential temperature controller.
 Manually switch the circulation pump ON and OFF via the solar differential 
temperature controller (see section, manual operation, page 27) to pump fluid 
around the solar primary system.
Turn the pump off and open the airbleed screw on the air separator 
(Fig. 22 Item 1).
Bleed any air from the air separator.
If the system pressure drops top up by opening the fill and drain valve 
(Fig. 22 Item 2) on the safety group and pumping in more solar fluid to restore 
the pressure. This must be repeated until the pressure remains stable.

Setting the system pressure
During commissioning, the system pressure should be 0.7 bar above the static 
pressure (1 metre height differential equals 0.1 bar). However, it must be at least 
1.5 bar and no higher than 2.2 bar.
 Determine the system pressure when the system is cold (20°C). This should be 
recorded on the Commissioning Record Sheet.
 If the pressure is too low you should pump additional heat transfer fluid into the 
system; the fill & drain valve on the safety group (Fig. 22 Item 2) needs to be 
opened for this purpose. When system pressure is correctly set, ensure the fill and 
drain valve is closed and remove filling hose from safety group.

17

© Baxi Heating UK 2012

8.0

Commissioning of system

8.1

Air Test

1. An air test may be used on the pipework to detect any gross
leakage prior to flushing and filling with solar heat transfer fluid.
Pressurise the system to a maximum of 1 bar to check for leaks.

2. Ensure that the solar expansion vessel pre-charge pressure
has been set prior to flushing and filling. 

8.2

Flushing and Filling the pipework

1. Before the system is commissioned the pipework must be
flushed to remove any contaminants. 

This must be done using

the solar heat transfer fluid as it will be impossible to fully
drain all parts of the system.

2. Connect the flushing pipes to the fill & drain valve on the
safety group (Fig. 19 Item 1) and to the fill & drain valve on the
flow meter (Fig. 19 Item 2).

3. Open the fill & drain valves.

4. Turn the slot of the adjusting screw (Fig. 19 Item 3) in the
return so the slot is vertical to open the non-return valve.

5. Turn the left hand isolating valve with integral thermometer in
the flow (Fig. 19 Item 4) in the direction indicated by the arrow
(to a 45° position) to open the non-return valve.

6. Ensure that the right hand isolating valve with integral
thermometer in the return (Fig. 19 Item 5) is open indicated by
the dot on the thermometer bezel being at the top.

7. Turn the slot of the flow meter adjusting screw (Fig. 19 Item
6) in the return vertically to open the flow limiter (Fig. 19 Item
7).

8. Flush the solar primary pump by pumping the fluid into the
system via the fill and drain valve on the safety group (Fig. 19
Item 1). 

9. Close right hand isolating valve (dot on thermometer bezel at 
9 o’clock position). Flush solar primary pipework and collector
via the fill and drain valve on the safety group. 

If reusing flushed

fluid ensure this is filtered before re-introducing into the
system.

(see Fig. 20). Use a suitable container of a large enough

volume to collect the fluid.

10. When satisfied that all pipework and component parts have
been thoroughly flushed, the system can be filled.

4

5

3

6

7

Fig. 19

Fig. 20

Fig. 21

Solar fluid

Filling pump

Filter

1

2

1

3

2

45°

Read at top
of float

Figure 21

Figure 22

1

2

Содержание Megaflo Eco SolaReady

Страница 1: ...ot Water Cylinders Megaflo Eco SolaReady Unvented Important Please read understand all these instructions before commencing installation Please leave this manual with the customer for future reference...

Страница 2: ...Direct model 17 Indirect model 18 Installation of solar differential temperature controller 21 East West Array Kit 22 Commissioning 23 Commissioning of solar primary system 24 Commissioning of hydraul...

Страница 3: ...nels its temperature is raised The heated fluid is circulated through a heat exchanger coil in the base of the Megaflo Eco SolaReady solar storage cylinder transferring the heat gained to the stored w...

Страница 4: ...L CAPABILITIES OR LACK OF EXPERIENCE AND KNOWLEDGE IF THEY HAVE BEEN GIVEN SUPERVISION OR INSTRUCTION CONCERNING USE OF THE APPLIANCE IN A SAFE WAY AND UNDERSTAND THE HAZARDS INVOLVED CHILDREN SHALL N...

Страница 5: ...team heating plant unless additional and appropriate safety devices are installed Ascending spray type bidets or any other Class 5 back syphonage risk requiring that a Type AA AB AD or AG air gap be e...

Страница 6: ...ELECTRICIAN AND BE IN ACCORDANCE WITH THE LATEST I E E WIRING REGULATIONS ENSURE THE ELECTRICAL SUPPLY IS SWITCHED OFF BEFORE MAKING ANY CONNECTIONS TO THE MEGAFLO ECO SOLAREADY The Environment This p...

Страница 7: ...to 40 C 260 248 300 Weight empty kg 60 7 69 1 75 4 Weight full kg 320 312 369 Volume Litres 259 243 294 Dedicated solar volume Litres 91 4 83 4 118 0 Max mains pressure 1 6 MPa 16 Bar Max design press...

Страница 8: ...s no requirement to site it close to the unit it can be located at a point where the mains supply enters the premises if this is more convenient but you must install a non return valve just after the...

Страница 9: ...e plumbed to the inlet connection of the Megaflo Eco SolaReady unit No other valve should be fitted between the Pressure Relief Expansion Valve and the cylinder inlet Outlet to Megaflo eco Solar Mains...

Страница 10: ...atmosphere see page 14 Discharge Pipework Isolating Regulating Valves as required Temperature Pressure Relief Valve HWS supply Balanced HWS and MCWS to bathrooms showers cloakrooms etc DOC DOC DOC DO...

Страница 11: ...f a secondary circulation system is required it is recommended that it be connected to the Megaflo Eco SolaReady as shown in Figure 7 To achieve this the 1 2 BSP Sensor Pocket must be removed The seco...

Страница 12: ...he discharge pipe should not be blocked or used for any other purpose The discharge connections from the Pressure Relief Expansion Valve and the Temperature Pressure Relief Valve must not be used for...

Страница 13: ...ter for prolonged periods should be used Worked example of discharge pipe sizing This example is for a G temperature relief valve with a discharge pipe D2 having 4 No elbows and length of 7m from the...

Страница 14: ...l outlet size of the safety device between 18 and 27m at least 3 sizes larger and so on bends must be taken into account in calculating the flow resistance See Diagram 1 Table 1 and the worked example...

Страница 15: ...s of up to 150 C The solar collectors panels or evacuated tubes must be installed according to the instructions supplied with those selected We can only guarantee the system performance if installed i...

Страница 16: ...water expansion vessel or boiler sealed system vessel The charge pressure of the solar expansion vessel must be adjusted when the fluid circuit is empty or de pressurised to a pressure equal to the st...

Страница 17: ...the event of a thermostat failure The thermal cut out reset button position is indicated on Figure 13 DO NOT BYPASS THE THERMAL CUT OUT IN ANY CIRCUMSTANCES The lower immersion heater can be operated...

Страница 18: ...mostat and thermal cut out MUST NOT be disconnected or bypassed To do so would invalidate the product approvals and warranty and it would not comply with Building Regulations Should this method of con...

Страница 19: ...4 N N 1 2 GY BL BR GR OR L N Room stat CH 2 port valve CH pump Solar pump 11 12 A1 N 11 12 E Solar pump 1 L1 NOTE For boilers with pump over run CH pump live supply should be connected to terminal 5...

Страница 20: ...d N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Link Link Link 9 12 N 12 1 1 2 3 GY BL BR GR OR Cylinder auxiliary controls DHW 2 port valve N 7 8 N 8 11 5 4 N N 1 2 GY BL WH GR OR L N Room stat 3 port mid...

Страница 21: ...N Switched Output 2 Neutral A3 Switched Output Live 3 For Auxiliary Heat Control N Switched Output 3 Neutral PE Earth Connection T1 M1 Temperature Sensor Collector 1 Tc1 T2 M2 Temperature Sensor Stora...

Страница 22: ...n is on the East facing circuit The common return pipe from the solar pump station should be connected to the comman Port In the default position the valve is open to Port B When power is applied to t...

Страница 23: ...ct Units Switch on the electrical supply to the immersion heater s and allow the unit to heat up Check that the thermostat operates correctly A storage temperature of approx 60 C is recommended If nec...

Страница 24: ...drain valve on the safety group Fig 19 Item 1 Close right hand isolating valve dot on thermometer bezel at 9 o clock position Flush solar primary pipework and collector via the fill and drain valve o...

Страница 25: ...lot of the adjusting screw Fig 19 Item 3 back to the horizontal position Commissioning of hydraulic station Ensure the solar primary system is free from air Switch on the power supply to the solar dif...

Страница 26: ...e button is pressed and held the value increments continuously Scroll left Exit Cancel Scroll left in main menu Exit a menu Exit a menu item Cancel a value changed without saving it Access Down Access...

Страница 27: ...erature measuring point T6 only shown if connected No 1234 h Operating hours for charging storage tank Can be reset to 0h Yes 927 kWh Energy yield for storage tank Can be reset to 0h Yes Inclination e...

Страница 28: ...selection 0 Normal 230V pump 1 1 HE pump with non inverse PWM Alternatively DC control 2 2 HE pump with inverse PWM Alternatively DC control Energy yield measurement glycol type selection 0 Anro 6 Ty...

Страница 29: ...Kelvin h Operating hours kWh Productivity indication in kWh OVERVIEW OF DISPLAY AND OPERATING ELEMENTS Graphic symbol Description Indication in operation Measuring points assignment Temperature measur...

Страница 30: ...ircuit pump via PWM signal The controller emits a PWM signal at connection O1 for the control of PWM pumps jumper position PWM Base frequency 2 kHz approx 12 V approx 5 mA Non inverse PWM control Non...

Страница 31: ...erature limits possible If the difference between both measurement points exceeds the hystere sis set then A3 is activated In addition one may also define a maximum temperature for the energy consumer...

Страница 32: ...eze If the temperature at the anti freeze sensor line 12 drops below the set value the solar circuit pump is activated and heats the solar circuit using the heat exchanger in the storage tank Basic Se...

Страница 33: ...k dTmax is kept constant as much as possible At lower deviation of Storage tank dTmax the pump is operated with the lowest power till the switch off wave is reached 11 14 Thermostat heating 1 The ther...

Страница 34: ...rmal insulation Fig 26 Item 2 against the rear thermal insulation section Fig 26 Item 3 until it clips into place Benchmark Log Book On completion of the installation and commissioning procedures deta...

Страница 35: ...aximum storage temperature 65 C Storage tank 1 Switch on difference dTon 7 K Storage tank 1 Switch off difference dToff 3 K Storage tank 2 Maximum storage temperature 90 C Storage tank 2 Switch on dif...

Страница 36: ...ate Check solar expansion vessel charge pressure bar bar bar bar bar bar bar bar bar bar bar bar bar Check solar primary system pressure cold bar bar bar bar bar bar bar bar bar bar bar bar bar Check...

Страница 37: ...ly to the immersion heater s and shut down the boiler on indirect units Turn off the mains water supply to the Megaflo Eco SolaReady unit Attach a hosepipe to the drain cock having sufficient length t...

Страница 38: ...r The collector or the collector array must be checked serviced annually to check for any damage leaks or contamination In areas where there may be a build up of dirt on the collector only non abrasiv...

Страница 39: ...p Air in the system Vent system Flow meter defective If visible check whether the flywheel of the meter moves when the system is running Also displayed with energy yield measurement Grundfos sensor de...

Страница 40: ...t in event insufficient solar gain Check If tripped reset by pressing button Check Set to a CH programme Check Switch on supply to immersion heater Check boiler operation If faulty contact boiler manu...

Страница 41: ...termittent Is the discharge continuous and very hot YES YES NO NO Heating fault water may have cooled Blending valves set too low Thermostat settings too low Water from hot taps is lukewarm Contact an...

Страница 42: ...y sensor connections Are sensor cables laid alongside mains voltage cables Have sensor cables been lengthened with unshielded cable Do sensors give correct temperature v resistance readings Are temper...

Страница 43: ...mersion Heater Backnut 95 607 940 Immersion Heater Gasket 70 351 65 Immersion Heater Key 95 607 861 Immersion Heater Blanking Plug 95 605 881 Titanium Immersion Heater Upper 95 606 989 Titanium Immers...

Страница 44: ...3 Bar Inlet Control Valve 3 Bar Pressure Reducing Valve Complete Expansion Relief Cartridge 8 Bar Pressure Relief Valve Complete 95 605 893 Figure 19 Exploded View of 8 Bar Pressure Relief Valve Figu...

Страница 45: ...07 932 E Titanium Immersion Heater Upper 95 606 989 Direct Combined Thermostat and Thermal Cut Out 95 612 717 Gasket 95 611 822 Backnut 95 607 940 Terminal cover 95 614 119 See Figure 21 for Solar Con...

Страница 46: ...ket 95 611 822 Backnut 95 607 940 Terminal cover 95 614 119 C 1 2 BSP Sensor Pocket Assembly Short 95 607 938 A D E C Direct Combined Thermostat and Thermal Cut Out 95 612 717 A Mounting Plate Direct...

Страница 47: ...hermometer 0 120 Blue 5 7225264 Venting circuit DN25 6 720688701 Flow meter 2 15 l min 7 7225266 Pump PWM connector FCI Connector 2m 8 7225265 Pump power supply connector TE Superseal 2m 9 7222382 Gru...

Страница 48: ...ecial Product Division Units 9 10 Hexagon Business Centre Springfield Road Hayes Middlesex UB40 0TY Tel 0208 5730574 Parts Center Network 65 Business Park Bentley Wood Way Burnley Lancashire BB11 5ST...

Страница 49: ...SERVICING 49...

Страница 50: ...ansfer fluid details What type make of heat transfer fluid used System volume litres What is the fluid mix Water Glycol Frost protection provided to C Is the installation in a hard water area above 20...

Страница 51: ...SERVICING 51...

Страница 52: ...pply products that meet or exceed appropriate standards and building and water regulations To provide pre and post sales technical support To provide clear and concise warranty details to customers 36...

Отзывы: