The correct layout of the electrical plant under conditions of explosion protection, as well as the
correct switch on procedure, is the sole responsibility of the user of the plant.
The current valid explosion protection rules and security regulations must be adhered to and
must be under given circumstances checked by a competent person. Should the plant on the
order of the user be erected by a subcontractor, the plant must only be switched on after the
subcontractor has submitted an installation certificate as prove of the correct nature of the
installation, according to the relevant valid regulations.
The primary switch on of explosion protected plants or part of plants, as well as the subsequent
switch on after major adjustments or maintenance work, must be reported to the relevant
authorities by the owner.
18
Responsibility for the Safe Operation / Disclaimer