3. Installation
PNEG-765
In-Line Intermediate Discharge Gates
9
Cut Out Discharge Hole in Trough Bottom
NOTE:
Gates have slotted holes for slight adjustment.
1. Determine the location of the discharge and identify the specific intermediate section that must be
modified to mount the gate.
2. Measure from the intermediate flange connection and mark the centerline of the discharge on the
intermediate bottom (dimension “A”).
3. Refer to the trough hole dimensions chart for the required cut size for the gate opening,
dimensions “B” and “C”. Dimensional values are centered around the discharge location,
dimension “D” can be used as a reference.
4. Mark the opening outline on the intermediate bottom and verify the size with the gate opening prior
to cutting the material.
5. Clean up the cut with a grinder to remove burrs and rough edges. The gate’s carry-over bar frame
must be able to fit inside the opening.
Figure 3B
Trough Hole Dimensions
Conveyor Size
“B”
“C”
“D”
0912
9.00
30.125
1.50
1212
12.00
30.125
1.50
1612
16.00
30.125
1.50
1214
12.00
30.125
1.50
1614
16.00
30.125
1.50
2114
21.00
30.125
1.50
1420
14.00
36.125
2.00
1620
16.00
36.125
2.00
2020
20.00
36.125
2.00
2620
26.00
36.125
2.00
3220
32.00
36.125
2.00
2626
26.00
36.125
2.00
3226
32.00
36.125
2.00
3232
32.00
36.125
2.00
3632
36.00
36.125
2.00
Ref #
Description
A
Conveyor Bottom