MAIN COVER INSTALLATION

After the end panels are installed, install the main cover. 

The steps to install the main cover include:
1.  Attach poly latch U-Channel (102197) along the high 

tunnel sides and tops of the high tunnel end rafters 

using FA4482B Tek screws.

2.  Pull main cover over the frame. 
3.  Attach the main cover to the end rafters using the poly 

latch springs.

4.  Stretch and attach main cover to the sides of the frame.
5.  Install roll-up side kits and test the operation of the 

twist-of-the-wrist assembly.

INSTALL POLY LATCH U-CHANNEL (102197)

1.  Measure the desired height (4'-5') to identify the top 

of the roll-up sides. Attach the poly latch channel at 

approximately 4'-5' above the ground on both sides of 

the frame. 

 

RECOMMENDED:

 Attach a ribbon board 

(2" x 4" 

or 2" x 6")

 to the rafters and then attach the poly 

latch U-channel (102197) to the ribbon board using 

customer-supplied wood screws.  

NOTE:

 Ribbon board and baseboard (recommended) 

shown in the diagram above 

are not included

 and are 

supplied by the customer

. Use the supplied FAH009B 

(1/4" x 4") carriage bolts and FALB01B (1/4") nuts to 

secure the ribbon board and U-Channel to the rafter. 

Use customer-supplied wood screws to secure 

U-channel to ribbon board. Do not use Tek screws 

to attach U-Channel to wood.

 

 

NO RIBBON BOARD: 

Attach one section of the poly 

latch U-Channel to the side of the frame using Tek 

screws. Attach U-Channel flush with the outside edge 

of the end rafter at each end of the assembled frame.

ATTACH END PANELS

CAUTION:

 To prevent damage, do not install end

panels on a windy day. 

Gather parts:
•  28' x 28' end panel film (108657) cut in half.
•   Fabric clips #CC6213 (Divide quantity in half.)
•  Tape measure and scissors 

Assembly Procedure
1.  Cut end panel film (108657) in half to create two end 

panels (14' x 28' each) — one for each frame end.

2.  Spread one end panel film out on ground at desired 

end of frame and center as needed.

3.  With proper lift (or ladders), pull end panel up and over 

top of end rafter.

4.  Secure end panel to backside of end rafter at top, 

center position using a fabric clip and Tek screw.

5.  Moving outward in both directions, continue attaching  

fabric clips to secure end panel to rafter. Evenly space 

fabric clips and work toward ground.  

ATTENTION:

 Use half of the clips to secure end panel

6.  Repeat steps to secure remaining end panel to frame 

using remaining half of fabric clips. 

 

NOTE:

 Trim excess film material after installation. Do 

not trim too close to fabric clips; allow at least 6" to 

remain beyond clips. 

Shelter shown above may be a different model. 

Drawing used for illustration only. Actual number of 

clips may differ.

Содержание PB01700R6

Страница 1: ...s a different length but similar model Economy high tunnels include film roof and film end panels STK DIMENSIONS PB01700R6 26 W x 12 H x 48 L PB01710R6 26 W x 12 H x 96 L 2020 GrowSpan All Rights Rese...

Страница 2: ...manufacturer s warranty and may cause serious injury and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and pre...

Страница 3: ...equipped This applies to fabric covers that stretch over the frame assembly Your shelter may include roof panels or side panels or both 11 Read the Care and Maintenance information at the end of thes...

Страница 4: ...ed for buildings with roll up sides Materials for baseboards and ribbon boards are not included and are supplied by customer ATTENTION Fasteners to secure boards to building frame are included Recomme...

Страница 5: ...Screw Tek Screw Rafter The following graphics and photos will help you identify the different parts Some parts are not shown Swaged Plain Swaged and Plain Rafter Sections 102198 U Channel Spring CC62...

Страница 6: ...ly procedure 2 Assemble the rafters and frame and square the frame 3 Prepare and attach end panels 4 Attach main cover and roll up side crank assembly Ground Level End Rafter Inside Rafter Baseboards...

Страница 7: ...ore driving the remaining posts to the required height 8 After all corner posts are accurately installed tie a string line between the tops of the corner ground posts on the same side of the shelter T...

Страница 8: ...crews so they will not touch the cover once it is installed This is typically on the backside of the rafter which will be the surface visible from the inside of the high tunnel once the frame is assem...

Страница 9: ...the purlin pipe in the joint where the rafter pipes are connected to keep purlins aligned during assembly 7 Repeat the previous step to install a second purlin section See the above diagram for detai...

Страница 10: ...ign with the center of the end rafter for best results If the purlin is too short to fit into the rafter end clamps without pulling the end rafter out of plumb first verify you have the correct pipe I...

Страница 11: ...Continue by installing the remaining pipe and clamps BASEBOARD INSTALLATION RECOMMENDED Gather the parts Treated or recycled plastic lumber supplied by customer Recommended 2 x 6 1 4 x 4 carriage bolt...

Страница 12: ...r supplied wood screws to secure U channel to ribbon board Do not use Tek screws to attach U Channel to wood NO RIBBON BOARD Attach one section of the poly latch U Channel to the side of the frame usi...

Страница 13: ...nd pull the cover into place Center cover side to side and end to end IMPORTANT To prevent damage to the main cover during installation additional personnel and lifts may be needed INSTALL POLY LATCH...

Страница 14: ...h edges of the first end rafter until the entire length of the end of the main cover is secured in place 7 Stretch the cover to the other end of the building and repeat the steps to secure the main co...

Страница 15: ...cover 3 Assemble and install the crank assembly 4 Install the Anti Billow Rope system 5 Test the operation of the roll up side 4 Place the assembled conduit at the base of the side where the end of t...

Страница 16: ...cted using wood boards under each rafter foot or if baseboards were installed If the shelter was constructed on concrete footings a concrete slab or on bare ground alternative steps must be taken by t...

Страница 17: ...fore reassembling For replacement or missing parts call 1 800 245 9881 for assistance 4 Attach the remaining eyebolts using the diagram above as a pattern guide 5 Once all eyebolts are installed in th...

Страница 18: ...01 20 QUICK START GUIDE 26 Wide Round Economy High Tunnels 26 0 Width 12 6 15 16 Heigth F FR RO ON NT T Grid Represents 12 Squares Ground Level Diagram shows a different length but similar model Econ...

Страница 19: ...01 26R1602 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 ATTENTION Except fo...

Страница 20: ...Y HIGH TUNNELS Revision date 01 01 20 7 131S075 1 131P0735 48 0 Length Customer Supplied Baseboards Customer Supplied Ribbon Boards Purlin Run 6 0 on center Rafter Spacing center to center SIDE PROFIL...

Страница 21: ...HIGH TUNNELS Revision date 01 01 20 SIDE PROFILE PB01710R6 6 0 on center Rafter Spacing 96 0 Length center to center 15 131S075 1 131P0735 Purlin Run Customer Supplied Baseboards Customer Supplied Ri...

Страница 22: ...View 1 End Rafter Purlin Connection Purlin 102548 Rafter View 2 Mid Rafter Purlin Connection Purlin ATTENTION Install a Tek screw through each clamp into the rafter and through each clamp into the pu...

Страница 23: ...23 GROWSPAN ROUND ECONOMY HIGH TUNNELS Revision date 01 01 20 Space below is reserved for customer notes...

Отзывы: