10

GROWSPAN

 ROUND ECONOMY HIGH TUNNELS

Revision date: 01.01.20

10. Move to 

the last two rafter joints

 and install the first 

section (#131S075) of those purlins. Verify the rafter 

spacing is 6' on-center, and tighten the end clamps 

and cross connectors. 

Do not install the top, center 

purlin until the entire frame is assembled. 

FRAME ASSEMBLY (continued)

NOTE:

 Each purlin assembly consists of 1.315'' x 75'' 

(#131S075) swaged pipes (quantity is determined by 

shelter length) and one (1) 1.315'' x 73.5'' (#131P0735) 

plain pipe to end each purlin run.  

 

Consult the Side Profile diagram in the Quick Start 

section for your building for additional details.

11.  Continue adding rafters and purlin pipe until the frame 

is assembled. 

Secure each purlin splice using a Tek 

screw. See diagram that follows.

12. Finish each purlin run using the plain, pipe 

(#131P0735), and use the final end rafter to complete 

the assembly. If the last end rafter is plumb and the 

purlin run extends beyond the end of the rafter, cut the 

last section of purlin pipe to the required length. 

Install next two purlins at the 

rafter joints in the locations circled 

in this diagram. Dashed lines 

represent the next purlin pipes.

NOTE:

 Typically purlin pipes 

do not

 require cutting. 

Verify that you have the correct plain pipes before you 

decide to cut any pipe to complete the purlin runs. 

 

 

To prevent cover damage, do not allow the plain end of 

any purlin to extend beyond the end of the end rafter. 

Align with the center of the end rafter for best results. 

 

If the purlin is too short to fit into the rafter end clamps 

without pulling the end rafter out of plumb, first verify 

you have the correct pipe. If so, loosen a purlin splice 

and slide the pipes apart. At least half of the tapered 

end must remain inside the adjacent pipe. Drive the Tek 

screw back into the pipe to secure the purlin joint.

13. Once all rafters are set and the four (4) lower purlins 

are in place and secured, return to each pipe splice 

of each purlin run and verify that a Tek screw secures 

each joint. Install a Tek screw (if needed).

14. Continue by installing the top, center purlin. 

Position the bolt side of the end clamps toward the 

inside of the shelter—the same side as the purlin. 

INSTALL TOP, CENTER PURLIN

Complete the following steps:
1.  Move to one end of the assembled frame, find the 

center of the end rafter, and mark the top, center 

location on the outside face of the end rafter. 

2.  Move to the other end of the frame and repeat the step 

to find the top, center of that end rafter.

3.  To keep the top purlin parallel with the lower purlins, 

take a chalk line, stretch it between the two marks, and 

snap it to mark the position of the top purlin. 

 

NOTE:

 For buildings longer than a typical chalk line, 

find the center of an interior rafter and snap the chalk 

line using that mark and the mark on the end rafter. 

Repeat as needed to mark all rafters. 

 

Position purlin on the underside of the frame to match 

the other purlins. See detail to the left.

Mark the center of the end 

rafter at both ends to position 

the top, center purlin.

To the 

inside of 

the shelter

End Rafter

Содержание PB01700R6

Страница 1: ...s a different length but similar model Economy high tunnels include film roof and film end panels STK DIMENSIONS PB01700R6 26 W x 12 H x 48 L PB01710R6 26 W x 12 H x 96 L 2020 GrowSpan All Rights Rese...

Страница 2: ...manufacturer s warranty and may cause serious injury and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and pre...

Страница 3: ...equipped This applies to fabric covers that stretch over the frame assembly Your shelter may include roof panels or side panels or both 11 Read the Care and Maintenance information at the end of thes...

Страница 4: ...ed for buildings with roll up sides Materials for baseboards and ribbon boards are not included and are supplied by customer ATTENTION Fasteners to secure boards to building frame are included Recomme...

Страница 5: ...Screw Tek Screw Rafter The following graphics and photos will help you identify the different parts Some parts are not shown Swaged Plain Swaged and Plain Rafter Sections 102198 U Channel Spring CC62...

Страница 6: ...ly procedure 2 Assemble the rafters and frame and square the frame 3 Prepare and attach end panels 4 Attach main cover and roll up side crank assembly Ground Level End Rafter Inside Rafter Baseboards...

Страница 7: ...ore driving the remaining posts to the required height 8 After all corner posts are accurately installed tie a string line between the tops of the corner ground posts on the same side of the shelter T...

Страница 8: ...crews so they will not touch the cover once it is installed This is typically on the backside of the rafter which will be the surface visible from the inside of the high tunnel once the frame is assem...

Страница 9: ...the purlin pipe in the joint where the rafter pipes are connected to keep purlins aligned during assembly 7 Repeat the previous step to install a second purlin section See the above diagram for detai...

Страница 10: ...ign with the center of the end rafter for best results If the purlin is too short to fit into the rafter end clamps without pulling the end rafter out of plumb first verify you have the correct pipe I...

Страница 11: ...Continue by installing the remaining pipe and clamps BASEBOARD INSTALLATION RECOMMENDED Gather the parts Treated or recycled plastic lumber supplied by customer Recommended 2 x 6 1 4 x 4 carriage bolt...

Страница 12: ...r supplied wood screws to secure U channel to ribbon board Do not use Tek screws to attach U Channel to wood NO RIBBON BOARD Attach one section of the poly latch U Channel to the side of the frame usi...

Страница 13: ...nd pull the cover into place Center cover side to side and end to end IMPORTANT To prevent damage to the main cover during installation additional personnel and lifts may be needed INSTALL POLY LATCH...

Страница 14: ...h edges of the first end rafter until the entire length of the end of the main cover is secured in place 7 Stretch the cover to the other end of the building and repeat the steps to secure the main co...

Страница 15: ...cover 3 Assemble and install the crank assembly 4 Install the Anti Billow Rope system 5 Test the operation of the roll up side 4 Place the assembled conduit at the base of the side where the end of t...

Страница 16: ...cted using wood boards under each rafter foot or if baseboards were installed If the shelter was constructed on concrete footings a concrete slab or on bare ground alternative steps must be taken by t...

Страница 17: ...fore reassembling For replacement or missing parts call 1 800 245 9881 for assistance 4 Attach the remaining eyebolts using the diagram above as a pattern guide 5 Once all eyebolts are installed in th...

Страница 18: ...01 20 QUICK START GUIDE 26 Wide Round Economy High Tunnels 26 0 Width 12 6 15 16 Heigth F FR RO ON NT T Grid Represents 12 Squares Ground Level Diagram shows a different length but similar model Econ...

Страница 19: ...01 26R1602 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 ATTENTION Except fo...

Страница 20: ...Y HIGH TUNNELS Revision date 01 01 20 7 131S075 1 131P0735 48 0 Length Customer Supplied Baseboards Customer Supplied Ribbon Boards Purlin Run 6 0 on center Rafter Spacing center to center SIDE PROFIL...

Страница 21: ...HIGH TUNNELS Revision date 01 01 20 SIDE PROFILE PB01710R6 6 0 on center Rafter Spacing 96 0 Length center to center 15 131S075 1 131P0735 Purlin Run Customer Supplied Baseboards Customer Supplied Ri...

Страница 22: ...View 1 End Rafter Purlin Connection Purlin 102548 Rafter View 2 Mid Rafter Purlin Connection Purlin ATTENTION Install a Tek screw through each clamp into the rafter and through each clamp into the pu...

Страница 23: ...23 GROWSPAN ROUND ECONOMY HIGH TUNNELS Revision date 01 01 20 Space below is reserved for customer notes...