Ultra Heat GMV VRF Technical Service Manual INSTALLATION
22
4 ONSITE REVIEW OF DESIGN DRAWING
Installation personnel must carefully read and understand the design scheme and drawings
provided by engineering designers, and prepare detailed and feasible construction organization design
after reviewing the onsite status.
The following aspects of working drawing must be reviewed:
(1) The loads of indoor and ODUs must match. The gross rated capacity of the IDU should be set
to a value that is 50% to 135% of the rated capacity of the ODU. In actual conditions, if the capacity of
concurrently operating IDUs exceeds 100% of the rated capacity of the ODU, the air conditioning system
fails to meet the requirement. Note: Configuration in excess of the capacity of the IDUs can affect the
comfort for users. The more the excess is, the lower the adjustment capacity of an air conditioning unit
will be. The difference of level between an ODU and an IDU, and that between IDUs must be set within
the designed range.
(2) The pipe diameter and manifold type in the cooling system must meet relevant technical
specifications.
(3) The drainage method of unit condensate water must be reasonable; the pipeline slope must
follow the design requirement of unit.
(4) The air duct direction and air flow are reasonably organized.
(5) The configuration specifications, type, and control method of power cables should meet the
design requirement of unit.
(6) The arrangement, total length, and control method of control line should meet the design
requirement of unit.
NOTE:
Engineering construction personnel must strictly abide by the design drawings. If any design
cannot be implemented during construction and needs to be modified, contact the designer first for
approval and prepare a written document, that is, the design modification record.
Содержание Ultra Heat GMV-V72W/A-F
Страница 1: ...Ultra Heat GMV Multi VRF TECHNICAL SERVICE MANUAL R410A Heat Pump Series...
Страница 22: ...Ultra Heat GMV VRF Technical Service Manual INSTALLATION 17 CHAPTER 2 INSTALLATION...
Страница 26: ...Ultra Heat GMV VRF Technical Service Manual INSTALLATION 21...
Страница 77: ...Ultra Heat GMV VRF Technical Service Manual COMMISSIONING OPERATION 72 CHAPTER 3 COMMISSIONING OPERATION...
Страница 105: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 100 CHAPTER 4 MAINTENANCE...
Страница 116: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 111...
Страница 117: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 112 2 System high pressure protection E1...
Страница 118: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 113 3 System low pressure protection E3...
Страница 119: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 114 4 System refrigerant lacking protection U4...
Страница 121: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 116 7 Temperature sensor fault 8 Pressure sensor fault...
Страница 149: ...Ultra Heat GMV VRF Technical Service Manual MAINTENANCE 144 6 Install a new compressor drive screw and wire it PFC board...
Страница 180: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 175 CHAPTER 5 REMOTE CONTROL...
Страница 186: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 181 2 Set software installation catalogue...
Страница 191: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 186 5 USING DEBUGGER 5 1 Manual for Initial Usage...
Страница 206: ...Ultra Heat GMV VRF Technical Service Manual REMOTE CONTROL 201...
Страница 239: ......
Страница 240: ...Jf00303483...