4. Place the packing base ring (6-152-0) into the
stuffing box. Slide the stuffing box cover over
the pump shaft, and, if applicable, bolt the
stuffing box to the motor adapter using
capscrews (1-904-0).
5. Install the packing (6-924-0) and, if applicable,
the seal cage ( 6-013-0) into the stuffing
box being sure to stagger the joints as per
the instructions found in the general pump
instruction section of this book.
Impeller installation
1. If the pump is equipped with mechanical seals,
slide the spacer sleeve (1-154-0) over the shaft
sleeve and into the stuffing box.
2. Install the impeller key into the keyway on the
impeller side of the motor shaft.
3. Slide the pump impeller (4-002-0) onto the
motor shaft.
4. Screw the impeller nut (4-023-0) onto the pump
shaft until finger tight. Hold the outside diameter of
the impeller and tighten (clockwise as viewed from
the suction inlet) the impeller nut to 25-30 ft. lbs.
5. For pumps with mechanical seals, tighten gland
evenly against the stuffing box.
Final assembly
NOTE: When assembling the rotating assembly to
the casing, be certain that the pump feet
are parallel to the motor feet.
1. Place the "0" ring casing seal (2-914-0) around
the "0" ring seat on the stuffing box cover.
2. Carefully slide the motor, motor adapter, stuffing
box assembly into the casing being sure not to
pinch the "0" ring. Insert the capscrews (1-904-0)
through the frame and into the casing (the large
Series A-C 2000 pumps use capscrews and
clamping lugs (1-937-0) to hold the motor adapter
to the casing. Tighten opposite capscrews evenly
around the adapter until the stuffing box has been
drawn evenly into the casing). Then, alternately
torque each capscrew to 25 ft. lbs.
3. If necessary, connect the suction and discharge
piping to the pump.
4. Secure the motor foot.
5. Connect the flushing water system to the stuffing
box.
6. If the pump is to be started, be sure flushing is
provided to the stuffing box.
7 . Connect the power to the motor. CHECK THE
MOTOR ROTATION.
This completes the assembly of the Series A-C 2000
close-coupled pump.