6. Commissioning
Before commissioning you have to check if the connection data of the device match the data
of the plant (see nameplates).
If so, you can start to put the device into operation by switching on the power supply and the
measurement inputs.
Measurement input
Input voltage
Input current
System frequency
1 Works no.
2 Test and conformity marks
3 Assignment voltage inputs
4 Assignment current inputs
5 Assignment power supply
6 Load capacity relay outputs
6.1 Operating LED
The operating LED shows the present device state.
Procedure
LED display
Booting of device
•
Flashes green (1 Hz)
•
If successful: Change to static green display
Firmware update
•
Change to update mode: Static red
•
During update: Flashes red (1 Hz)
•
If successful or cancelled: Booting of device
Factory reset or reset of communication
settings
•
During reset: Flashes red (1 Hz)
•
Then: Booting of device