44
2000225065A
14 Replacement of Parts
14.38 Hydroblock Assembly Right-Hand
For access, refer to section 14.1.
Refer to section 12.9 to drain the boiler heating circuit.
Refer to section 12.10 and drain the boiler hot water circuit.
Refer to diagram 14.26.
Undo the connector on the bottom of the return pipe from the
hydroblock.
Undo the nut connecting return pipe to heat exchanger.
Lift the return pipe up out of the way.
Undo the coupling at the base of the expansion vessel, see
diagram 14.10.
Remove the clip holding the expansion vessel coupling into the
top of the right hand hydroblock.
Move the coupling out of the way.
Remove pump head, refer to section 14.16.
Note: It is not necessary to disconnect the electrical lead but put
pump head in a convenient place where it will not strain the lead.
Remove the filling loop tube, refer to section 14.26.
Remove the bypass tube, refer to section 14.25.
Remove the electrical connections to the flow sensor and the
low water pressure sensor, refer to sections 14.23 and 14.24.
Remove the water connection clips 3 and 4 below the hydroblock,
see diagram 14.26.
Remove the central heating filter, refer to section 12.8.
Remove the retaining clip to remove the drain point, refer to
section 14.32.
Undo two securing screws on underside of the right hand
hydroblock.
Remove right hand hydroblock from plate-to-plate heat
exchanger using a TORX screwdriver to remove the securing
screw, see diagram 14.26.
Lift out the right hand hydroblock.
Remove the remaining components for refitting into the
replacement right hand hydroblock.
Refill, vent and pressurise the boiler.
Open the cold-water isolation valve and slowly open a hot water
tap to remove air. Close the hot water tap.
Check for leaks.
14.39 Access to Switches, User Interface and
Timer
For access, refer to section 14.1.
Release the front of the fascia by carefully prising up the two
retaining latches, see diagram 14.28.
Do not allow the front of the fascia to swing down and be loosely
held by the electrical connections to the mains/reset switch,
user interface and clock. Either remove the connections or
support the fascia.
14.40 Clock/Timer (if fitted)
Refer to section 14.39 for access.
Remove electrical plug.
Undo two securing screws and withdraw clock/timer.
14.41 Mains/Reset Switch
Refer to section 14.39 for access.
Remove the switch retaining screw.
Remove switch from housing, see diagram 14.29.
Remove electrical leads.
Diagram 14.27
Diagram 14.28
RETAINING
LATCHES
DIVERTER
VALVE
DIVERTER
VALVE
L.H. HYDROBLOCK
10101