3
V1.4 March 15
CONTENTS
Page
1.0
INTRODUCTION
5
1.1
Applications
5
1.2
Advantages
5
2.0 CONFORMITY
6
3.0 MARKINGS
6
4.0 DELIVERY
7
4.1
Packaging
4.2
Handling
4.3
Inspection
4.4
Storage
5.0
COMPONENTS
&
ASSEMBLY
8
5.1
QJ
Casing
sections
8
5.2
End
caps
10
5.2.1
Standard
cap
10
5.2.2
Grout
valve
cap
10
5.2.3
Grout
anchor
cap
11
5.2.4
Grout anchor with valve cap
11
5.2.5
Top
cap
12
5.2.6
Protection
12
5.3
Telescopic
joint
13
5.4
Repair
coupling
14
5.5
GXM 300I Combined settlement system
15
6.0
INSTALLATION
PLANNING
16
6.1
Installation considerations - all install types
17
6.2
Alignment
7.0 INSTALLATION - VERTICAL BOREHOLE
17
7.1
Borehole depth & cleanliness
17
7.2
Installation
overview
18
7.3
Buoyancy
19
7.4
Grouting
19
7.5
Grouting
methods
21
7.5.1
Pre-grouting with external grout pipe
21
7.5.2
Post-grouting with external grout pipe
22
7.5.3
Post-grouting with a
grout
valve
23
7.6
Installation
procedure 24
7.6.1
First
section
24
7.6.2
Subsequent sections
26
7.7
Orientation 28
7.8
Removing
temporary
casing
28
7.9
Protection
28