Generac Power Systems 006873 Скачать руководство пользователя страница 7

Section 2: General Information and Setup

Owner’s/Installation Manual for SMM

3

Section 2: General Information and Setup

Load Management Options

Load management systems are designed to work
together to prevent a generator from being overloaded by
large appliance loads. Options include:

Smart Management Modules (SMM)

Smart A/C Module (standard in single-phase 100-
800 Amp RTS transfer switches)

These options can be used in conjunction or separately.

Application Considerations

Generator overload condition is determined by generator
frequency. Loads are shed when frequency drops below
a preset value for a predetermined time.

A Smart Management Module (SMM) can be used
individually or in conjunction with a Smart A/C Module to
manage a combined total of eight loads. Smart
Management Modules operate independently when used
in conjunction with the Smart A/C module. 

Use Priorities A/C 1-4 on the Smart A/C Module as
the top priorities, then up to four Smart
Management Modules as Priorities 5-8.

Use only select A/C priorities on the Smart A/C
Module as the top priorities, then use additional
Smart Management Modules as the remaining
priorities.

To reduce the loads returned to the generator all at
once, it is best to set the SMM priorities to follow
after the last HVAC load has returned. This allows
the generator to accept loads gradually, reducing
the potential for additional nuisance load shed
events.

A Smart Management Module can share a priority
with an A/C priority on the Smart A/C Module
provided the generator is sized to handle the
combined surge load from both appliances. 

Sharing priorities can allow up to 12 loads to be
managed in a properly sized system.

In any combination of modules, the recovery times after a
loss of utility power or shutdown due to overload are
shown in 

Table 2-1

.

NOTE: 

For digital thermostats where a 24 VAC

thermostat wire is not available, an SMM must be used to
break the power at the HVAC load itself.

Smart Management Module

Any loads, including central air conditioners, can be
managed using a Smart Management Module (SMM).
The system can accommodate up to eight individual
SMM modules.

NOTE: 

SMM modules are self-contained and have

individual built-in controllers.

Smart A/C Module 

(Inside Transfer Switch)

Up to four air conditioner loads can be managed by the 
Smart A/C Module. The Smart A/C Module manages the 
loads by “shedding” the connected loads in the event of a 
drop in generator frequency (overload). Loads to be shed 
are in 4 priority levels on the module. 
Priorities A/C 1-4 (A in 

Figure 2-1

) have connections for

an air conditioner. To control an air conditioner, no
additional equipment is required. Internal normally closed
relays interrupt the 24 VAC thermostat control signal to
disable the air conditioner load.
Four LEDs, located on the Smart A/C Module (B in 

Figure 2-1

), illuminate when the output is activated to 

enable the load.
The Smart A/C Module has a test button used to simulate 
an overload condition (A in 

Figure 2-2

). This button 

operates even when the transfer signal is inactive.

Smart Management 
Module

<58 Hz for 3.5 seconds 
or <50Hz for 1 second

Smart A/C Module

<58 Hz for 3 seconds or 
< 50Hz for 0.5 seconds

Table 2-1. Priority Settings

Priority

Recovery Time

Smart A/C 

Module

Smart 

Management 

Module

1

5 minutes

Yes

Yes

2

5 minutes 15 seconds

Yes

Yes

3

5 minutes 30 seconds

Yes

Yes

4

5 minutes 45 seconds

Yes

Yes

5

6 minutes 

NA

Yes

6

6 minutes 15 seconds

NA

Yes

7

6 minutes 30 seconds

NA

Yes

8

6 minutes 45 seconds

NA

Yes

Содержание 006873

Страница 1: ...in death or serious injury Owner s Installation Manual Smart Management Module SMM SAVE THIS MANUAL FOR FUTURE REFERENCE MODEL 006873 DATE PURCHASED ______________ WWW GENERAC COM 1 888 GENERAC 1 888...

Страница 2: ...tains or emits chemicals known to the state of California to cause cancer birth defects and other reproductive harm 000004 WARNING California Proposition 65 Engine exhaust and some of its constituents...

Страница 3: ...3 Smart Management Module 3 Smart A C Module Inside Transfer Switch 3 Know Your Smart Management Module and Carton Contents 4 Section 3 Installation Tests and Troubleshooting Electrical Specification...

Страница 4: ...Table of Contents iv Owner s Installation Manual for SMM This page intentionally left blank...

Страница 5: ...RAC RESERVES THE RIGHT TO MODIFY THIS MANUAL AT ANY TIME Safety Rules The manufacturer cannot anticipate every possible circumstance that might involve a hazard The warnings in this manual and on tags...

Страница 6: ...Section 1 Introduction and Safety 2 Owner s Installation Manual for SMM This page intentionally left blank...

Страница 7: ...ed in a properly sized system In any combination of modules the recovery times after a loss of utility power or shutdown due to overload are shown in Table 2 1 NOTE For digital thermostats where a 24...

Страница 8: ...power See Table 2 2 NOTE Recovery time is based on priority dial settings See Table 2 1 Test Button C Disables contactor output for a specified time LED D Provides module status See Table 2 3 Contacto...

Страница 9: ...f Generator Module detected an overload while trying to recover from a shed situation It identified the offending load and disabled operation for 30 minutes to allow other loads to operate This state...

Страница 10: ...or after a shed the module will wait another 5minutes plus Priority delay before attempting to enable Note 2 The Checks power source block monitors frequency and will change state Generator or Utility...

Страница 11: ...against rain and sleet and is undamaged by the formation of ice on the enclosure 1 Turn OFF both UTILITY NORMAL and EMERGENCY STANDBY power supplies 2 Choose mounting location near electrical panel a...

Страница 12: ...ce The unit is now ready to configure apply power and perform testing Setting Priorities High priority 240 VAC loads should be set to the highest priorities so those loads recover first in the event o...

Страница 13: ...d priority time elapses each contactor will CLOSE and LED will illuminate and stay ON 7 Once LED stays ON press TEST button and verify load shed occurs 8 Once load shed occurs LED will flash at one se...

Страница 14: ...ator while attempting recovery from a shed It is in a 30 minute lockout wait period Wait 30 minutes from lockout for unit to attempt to re apply load Review all loads enabled in household The generato...

Страница 15: ......

Страница 16: ...c All rights reserved Specifications are subject to change without notice No reproduction allowed in any form without prior written consent from Generac Power Systems Inc Generac Power Systems Inc S45...

Отзывы: