Section 3: Installation, Tests and Troubleshooting

Owner’s/Installation Manual for SMM

9

An example configuration is shown below. Configurations
will vary depending on customer prioritization of loads:

1.

Set the priority of each SMM module as desired
(using the example configuration for reference).

2.

Apply priority decal in a suitable location on
electrical panel to record chosen priority
designations.

3.

Record priorities on decal.

Setting Lockout

Most installations will require the lockout switch to be
DISABLED. When performing a whole house backup
with a generator not sized to manage all household
loads, SMM's can be used to disable appliances or
circuits during an outage. For non-essential loads that will
not be used on generator power, set lockout switch to
ENABLED.

Tests

Utility Test

1.

Turn utility power ON and enable all module
feeding circuits.

2.

Verify LED begins to flash at one second intervals.

3.

All contactors will close after five minutes. LED will
illuminate, and stay ON.

Generator Test

1.

Simulate a utility loss by turning main line circuit
breaker (MLCB - service disconnect) OFF while
generator is in AUTO.

2.

All modules will lose power and LEDs will disable. 

3.

Generator will power on after preset delay. 

4.

All LEDs will flash when generator transfers.

5.

Allow each module to enable output per its priority
setting.

6.

After predefined priority time elapses, each
contactor will CLOSE and LED will illuminate and
stay ON.

7.

Once LED stays ON, press TEST button and verify
load shed occurs.

8.

Once load shed occurs, LED will flash at one
second intervals.

9.

Allow time for each module to enable contactor
output per priority setting.

10.

After predefined priority set time, each contactor
will CLOSE and LED will illuminate and stay ON.

NOTE: 

Depending on load size, the SMM module may

immediately go into load shed mode or lockout during
test. In this event, remove one or more higher priority
loads to allow testing of each module.

Generator Test with Lockout Switch Enabled 
(perform if Lockout Switch Enabled on any 
loads)

1.

Simulate a utility loss by turning MLCB (service
disconnect) to OFF while generator is in AUTO.

2.

All modules will lose power and LEDs will disable. 

3.

Generator should power on after preset delay. 

NOTE: 

For modules with lockout switch enabled, LEDs

will flash at six second intervals and load will remain
disabled while in generator power.

Return to Utility Test

1.

Return utility power by setting the MLCB (service
disconnect) to ON.

NOTE: 

All modules should begin flashing at one second

intervals.

NOTE: 

All modules will recover in five minutes (including

units with lockout switch enabled).

Installation Summary

Install cover on electrical panel.

Install covers on modules.

Priority 1 - Baseboard heat

Priority 5 - Non-essential 
circuits

Priority 2 - Air conditioner

Priority 6 - Pool pump or hot 
tub

Priority 3 - Range

Priority 7 - Other circuits

Priority 4 - Dryer

Priority 8 - Other circuits

Содержание 006873

Страница 1: ...in death or serious injury Owner s Installation Manual Smart Management Module SMM SAVE THIS MANUAL FOR FUTURE REFERENCE MODEL 006873 DATE PURCHASED ______________ WWW GENERAC COM 1 888 GENERAC 1 888...

Страница 2: ...tains or emits chemicals known to the state of California to cause cancer birth defects and other reproductive harm 000004 WARNING California Proposition 65 Engine exhaust and some of its constituents...

Страница 3: ...3 Smart Management Module 3 Smart A C Module Inside Transfer Switch 3 Know Your Smart Management Module and Carton Contents 4 Section 3 Installation Tests and Troubleshooting Electrical Specification...

Страница 4: ...Table of Contents iv Owner s Installation Manual for SMM This page intentionally left blank...

Страница 5: ...RAC RESERVES THE RIGHT TO MODIFY THIS MANUAL AT ANY TIME Safety Rules The manufacturer cannot anticipate every possible circumstance that might involve a hazard The warnings in this manual and on tags...

Страница 6: ...Section 1 Introduction and Safety 2 Owner s Installation Manual for SMM This page intentionally left blank...

Страница 7: ...ed in a properly sized system In any combination of modules the recovery times after a loss of utility power or shutdown due to overload are shown in Table 2 1 NOTE For digital thermostats where a 24...

Страница 8: ...power See Table 2 2 NOTE Recovery time is based on priority dial settings See Table 2 1 Test Button C Disables contactor output for a specified time LED D Provides module status See Table 2 3 Contacto...

Страница 9: ...f Generator Module detected an overload while trying to recover from a shed situation It identified the offending load and disabled operation for 30 minutes to allow other loads to operate This state...

Страница 10: ...or after a shed the module will wait another 5minutes plus Priority delay before attempting to enable Note 2 The Checks power source block monitors frequency and will change state Generator or Utility...

Страница 11: ...against rain and sleet and is undamaged by the formation of ice on the enclosure 1 Turn OFF both UTILITY NORMAL and EMERGENCY STANDBY power supplies 2 Choose mounting location near electrical panel a...

Страница 12: ...ce The unit is now ready to configure apply power and perform testing Setting Priorities High priority 240 VAC loads should be set to the highest priorities so those loads recover first in the event o...

Страница 13: ...d priority time elapses each contactor will CLOSE and LED will illuminate and stay ON 7 Once LED stays ON press TEST button and verify load shed occurs 8 Once load shed occurs LED will flash at one se...

Страница 14: ...ator while attempting recovery from a shed It is in a 30 minute lockout wait period Wait 30 minutes from lockout for unit to attempt to re apply load Review all loads enabled in household The generato...

Страница 15: ......

Страница 16: ...c All rights reserved Specifications are subject to change without notice No reproduction allowed in any form without prior written consent from Generac Power Systems Inc Generac Power Systems Inc S45...

Отзывы: