Initial commissioning
Initial commissioning checklist
2018-9015-005
09-2016
6.3
Initial commissioning checklist
This checklist must be completed by the dealer and the customer to validate that
the product is assembled and/or installed according to the manufacturer's
instructions and that it is safe for use.
Note!
Additional information necessary to complete the checklist can be
found in this instruction manual.
General
DONE
N/A
The owner received the instruction manual from the dealer and commits to read it.
The owner is instructed by the dealer on how to operate and maintain the product.
The safety guard/grid and safety labels are installed.
The signal lights are operational.
The lubrication points are lubricated.
The oil levels are adequate.
All bolts are torqued.
All drains are closed.
All connections are secured.
A visual inspection is performed to ensure there are no leaks, signs of distortion or defective parts.
The wheel nuts are tightened at correct torque.
The tires are inflated at appropriate pressure.
The tractor draw bar is adjusted to minimum length while respecting the PTO limitations.
The spreader impeller matches the tractor RPM.
The owner is instructed on the PTO driveline instructions.
The spare safety shear bolts are removed from the PTO guards.
The anti-siphon is in the upright position.
The owner is instructed on how to adjust the spreading flow rate using the PTO, the flow regulator, the
restriction plate, the directional valve and understands how to use the spreading chart.
The black film behind the spreader is removed.