Part II – Replacing the CPU
51
12
•
Apply power to the new CPU and allow 2 minutes for the device to self-initialize prior to
performing
Step 4
. If the new CPU is known to already have an IP address as specified in the
Step 4
dialog box, select the
Skip This Task
check box prior to clicking
Next
. Otherwise, leave
the check box cleared and just click
Next
.
Figure 12-10
Step 4 – Set Original IP dialog box
•
A confirmation dialog box will display asking for confirmation that the old CPU has been
replaced and the new CPU is installed and has been powered on for at least 2 minutes.
Figure 12-11
Entellisys LVS HMI dialog box
Содержание Entellisys DEH-230
Страница 1: ...GE Entellisys Low Voltage Switchgear System Administrator Manual ...
Страница 4: ......
Страница 8: ...System administrator roles and responsibilities 8 1 ...
Страница 10: ...Pre programming settings prior to switchgear arrival 10 2 2 ...
Страница 12: ...Commissioning the switchgear 12 3 ...
Страница 20: ...Time synchronization 20 5 ...
Страница 28: ...Installing and configuring remote HMI software 28 7 ...
Страница 32: ...Settings files and offline system configuration 32 8 Figure 8 3 Settings file compare screen ...
Страница 40: ...System archives 40 10 ...
Страница 44: ...Feature options 44 11 ...
Страница 54: ...Preparing and configuring a replacement CPU 54 12 ...
Страница 60: ...Other maintenance functions 60 13 ...
Страница 62: ......