Dealer Pre-Delivery & In-Field Commissioning Check List
The following must be carried out upon machine delivery to customer
Tick to confirm action
√
Customer has ensured that Machine is correct for the required application.
Customer has checked tractor specification to ensure machine is suited to tractor.
Customer has checked all items are received as per order.
Machine Assembled Correctly as per Operators Manual instructions.
Check Wheel Nuts for correct torque (refer maintenance section)
Tyre Pressures are correct as recommend.
Grease all grease nipples; hinges and wheel assembly pivots.
Check for Hydraulic Oil leaks.
Air purged from Hydraulic Circuits and tractor’s hydraulic oil level is OK.
Ensure Depth Control cylinders are phasing correctly (synchronized).
Ensure Machine is level front to rear
at working depth
.
Ensure Machine is level across the width.
Ensure lock nuts on depth control adjustment are locked tight.
Check for correct tractor to tow bar connection.
Implement safety chain fitted to tractor.
Ensure all shanks and press wheels set at consistent settings across machine, (If prac-
tical set machine to operator’s initial operation settings).
Check Air Seeder Distribution for kinks and obstruction through all working ranges
(where applicable).
Check row spacing is correct. (At initial operation, drive in straight line, lightly scratch-
ing machine along flat ground. Measure distance between marks).
Owner has viewed the Operators Manual.
Owner instructed on correct maintenance and safe operation of machine.
Owner and operators instructed on phasing cylinders depth stop use and
Owner and operators instructed to fully extending wing fold cylinders when operating.
Owner has agreed to train all operators in the safe use of the machine.
Pre delivery and in field commissioning by:
NAME:
DATE:
SIGNED:
Содержание NT8000
Страница 30: ...26 ...
Страница 31: ...27 Spare Parts SNT8000 HNT8000 Models ...
Страница 32: ...Spare Parts 28 ScariTILL Spring Tine Assembly ...
Страница 34: ...Spare Parts 30 HydraTILL Hydraulic Tine Assembly ...
Страница 38: ...Spare Parts 34 NT8000 Assembly ...
Страница 40: ...Spare Parts 36 Centre Frame Assembly ...
Страница 42: ...Spare Parts 38 Left Wing Assembly ...
Страница 44: ...Spare Parts 40 Right Wing Assembly ...
Страница 52: ...Spare Parts 48 Hydraulic System Wing Fold ...
Страница 54: ...Spare Parts 50 Hydraulic System Depth Control ...
Страница 58: ...Spare Parts 54 HydraTILL Plumb Kit 250mm Spacing ...
Страница 60: ...LAYOUTS 56 Layout 178mm Spacing 45 Tines ...
Страница 61: ...LAYOUTS 57 Layout 250mm Spacing 32 Tines Optional Presswheels Shown ...
Страница 62: ...LAYOUTS 58 Layout 308mm Spacing 26 Tines Optional Presswheels Shown ...
Страница 63: ...59 ...