RB-7-100 Page 11
SECTION 2
INSTALLATION
LOCATION
Install the blower in a well lit, clean dry place with plenty of room for inspection and maintenance.
FOUNDATIONS
For permanent installation we recommend concrete foundations be provided, and the equipment should be
grouted to the concrete. It is necessary that a suitable base be used, such as a steel combination base under
blower and motor, or a separate sole plate under each. Before grouting, equipment must be leveled, free of all
strains, and anchored so no movement will occur during setting of grout. After grout has completely hardened, a
recheck is necessary to compensate for shrinkage, etc. If required, add shims under blower feet after final
tightening of foundation anchor bolts to remove strain from the blower housing.
Where jack screws or wedges are used during grouting, they must be backed off and wedges removed before
final tightening of anchor bolts. Refer to grouting instructions.
Where a concrete foundation is not feasible, care must be taken to insure that equipment is firmly anchored to
adequate structural members, restricting movement and vibration.
MOUNTING CONFIGURATIONS
The blower flex-mount design enables horizontal and vertical mounting configurations with top or bottom hand,
right or left hand shaft positioning. The units are discharge timed allowing rotation in one direction
(refer to Figure 2-1).
REPOSITIONING THE MOUNTING FEET
1. Position the mounting feet to the desired location and snug the cap screw.
2. Place the blower on its feet on a flat surface.
3. Loosen mounting feet cap screws and level unit up. The bench or blower base flatness should be
within .002 of an inch.
NOTICE
If the unit is not flat within .002 of an inch, it will be necessary to shim the blower feet at installation.
Содержание RBS 15
Страница 1: ...PARTS LIST OPERATING AND SERVICE MANUAL RBS BLOWERS Models RBS 15 225 RB 7 100 Version 02 May 05 2017...
Страница 2: ......
Страница 16: ...RB 7 100 Page 15 RBS OVERHUNG LOAD...
Страница 26: ...RB 7 100 Page 25 SECTION 5 MAINTENANCE FIGURE 5 1 MAINTENANCE CHECK LIST...
Страница 29: ...RB 7 100 Page 28 SECTION 7 PARTS LIST 7 1 RBS 15 25 Sectional drawing FIGURE 7 1...
Страница 31: ...RB 7 100 Page 30 7 2 RBS 35 106 Sectional drawing FIGURE 7 2...
Страница 34: ...RB 7 100 Page 33 7 3 RBS 115 225 Sectional drawing FIGURE 7 3...
Страница 37: ...RB 7 100 Page 36 OVERHAUL KIT...
Страница 38: ...RB 7 100 Page 37...
Страница 39: ...RB 7 100 Page 38...
Страница 41: ......