37-1-613 Page 15
DISCHARGE PIPING
– In general, the type system used will govern the piping arrangement. However,
the following suggestions should be followed for blower protection and efficiency.
An expansion joint should be installed as close to the blower opening as possible to protect the blower
housing from stresses. All pipe connections should be square and even to prevent distortion from
misalignment.
An accurate pressure gauge must be provided near the blower discharge to indicate operation pressure.
If noise level is a factor, a discharge silencer should be used. The discharge line should be as straight
as possible. Where bends are necessary, use long radius fittings. Provision for condensate drainage at
the lowest point in the piping may be required.
VENTILATION –
If the blower is to operate in a housing or enclosure, proper ventilation must be
provided for adequate blower cooling. Cooling air should be taken from outside the enclosure.
OUTLINE DRAWINGS
– Certified outline drawings are available upon request. All important dimensions
are shown in Figure 2-4, page 16.
Содержание 5CDL-R Series
Страница 14: ...37 1 613 Page 13 FIGURE 2 3 BELT DRIVE OVERHUNG LOAD CALCULATIONS...
Страница 17: ...37 1 613 Page 16 TOP INLET MAIN ROTOR DRIVE FIGURE 2 4 OUTLINE DIMENSIONS...
Страница 30: ...37 1 613 Page 29 SECTION 5 PARTS LIST FOR LIST OF PARTS SEE PAGES 30 31 301CBH810 00 Ref Drawing...
Страница 40: ...37 1 613 Page 39 FIGURE 6 10 FIGURE 6 11 JACK SCREWS...