FOUNDATION
2.1.
Foundation Cube unit
The unit is equipped with transport rail, which allows to use forklifts for transport, loading and unloading. When the unit is installed
on site, a rail must be dismantled by unfastening 4 M8 screws situated near the rail from the electric box side and by pulling it out,
Doing so will allow canals installation on the bottom of the unit.
Cube units are built on self-supporting frame, which should be installed on brackets or frames connected to the roof, according to
construction law in specific country and must be ousted from roof slope to a height determined by this law. The manufacturer
determines unit’s installation on the unit’s contour in accordance with frame dimensions listed below. Installing on a supported
frame on two longer sides of unit’s frame.
Cube 20
demonstrative solution
•
Unit should be mounted to a frame in such way to ensure no move of unit. Using rubber pads between unit and frame
is highly advisable.
•
Install unit in such way that inlet and exhaust are not directed to windward.
•
The manufacturer allows installation on a frame with support on the two long sides of the unit's frame.
A [mm]
internal dim. 2180
B [mm]
internal dim. 1260
Содержание Rooftop Cube
Страница 1: ...www flowair com 1 Rooftop Cube SHORT ASSEMBLY INSTRUCTION v1 1 EN ...
Страница 2: ...2 www flowair com 01 2022r ...
Страница 57: ...www flowair com 57 Cube 80 100 Cube 80_100 L Cube 120 160 Cube R8 ...
Страница 59: ...www flowair com 59 01 2022r ...