6 - Electrical installation
Earthing
An external earthing electrode is required for the MVCS, for the construction of this electrode please follow local regulations as well as the
following minimum requirements:
• Minimum cross-sectional: depends on MVCS configuration, please consult FIMER.
• Installation depth: follow local standards
• Installation route around the MVCS = one mm from the outer wall
• Connect the MVCS earthing busbar to the earthing electrode. It is recommended to use joint lubricant to protect the connection point
against corrosion.
For more information, see grounding drawing “MVCS Grounding Layout”.
Protective earthing (grounding) inside the MVCS
The protective earth (PE) terminals or frames and metallic surfaces of the MVCS are connected to the main grounding busbar, please see
“MVCS Grounding Layout”.
At the installation site:
• Measure the continuity of all internal PE connections by measuring the conductivity between each protective earth terminal and the
main PE busbar.
• Earth the shields, armors, and protective conductors of all incoming cables to the appropriate earthing terminals of the station.
Measuring the insulation resistance of the cabling
Make sure that the insulation resistance of the external power cables is measured according to manufacturer recommendations and local
regulations.
Connecting the inverter inputs
To connect inverter cables to MVCS inputs (fuse holders), please check ac cables cross section, maximum cross section allowed in MVCS
is 3001 mm2 (defined by the fuse holders).
To connect the inverter inputs, follow the instructions below:
1. Make sure that all cables have the maximum cable size = 300 mm2.
2. Note that AC busbars are made in tinned copper, and so, if cables from the inverters are made in aluminum, then bi-metallic terminals
or washers are needed.
3. Considering the AC cable sizes and that the cables must be aligned with the fuse bases, mark the LV AC lead through holes in the cable
cover:
4. Remove the cable entry covers.
5. Drill holes of appropriate sizes in the AC cabinet cover and install cable glands to ensure that the IP degree of protection is maintained.
1) If bigger cross section is needed, please consult FIMER