Inspection Head Power Supply Check
55
Document 45277-0805
Inspection Head Power Supply Check
1.
Disconnect P1at the Inspection Head Power Supply Card.
2.
Make sure the UPS Circuit Breaker is in the Closed position.
3.
Turn CB3 ON and measure 24 VDC at PS6-P1 of Inspection
Head Power Supply card. See Drawing 41955 for this portion.
4.
Turn CB3 and off.
5.
Reconnect P1 and Inspection Head Supply card.
6.
Remove J2, j4, J5, J6, J7, J8, J9, J12 and J16.
7.
Turn on CB3 and check all of the LED’s on the top of the power
supply.
8.
Turn off CB3.
9.
Reconnect connectors disconnected in step 6.
Final installation of parts/assemblies
Base Strobe
Replace Base Strobe, Base Strobe Fan and connect all cables to
Strobe unit.
Air Panel
Replace air panel and re-connect to all hoses and signal
connector.
Powering up the Electronic Chassis
1.
Double check cables the power cables in the CPU Motherboard
NM1-P1A and MB1-P1B.
2.
Turn on all circuit breakers.
3.
Turn on the main power switch.
4.
Check to see that the system boots successfully.
Содержание Omnivision 1000 Series
Страница 1: ...Omnivision Upgrade Installation Manual Document 45277 0805...
Страница 3: ...2 Document 45277 0805...
Страница 4: ...3 Omnivision Upgrade Installation Manual Document 45277 0805...
Страница 8: ...4 Omnivision Upgrade Installation Manual Document 00805...
Страница 15: ...Machine Preparation 7 Document 45277 0805 Echain...
Страница 17: ...Machine Preparation 9 Document 45277 0805 Red Harness Yellow Column White Column BLUE COLUMN Plate 2 Location...
Страница 62: ...54 Omnivision Upgrade Installation Manual Document 45277 0805 5 Measure XFMR2 P1 for 220VAC 6 Turn Off CB12...
Страница 70: ...62 Omnivision Upgrade Installation Manual Document 45277 0805...