BOILER REPLACEMENT: MODENA 80/102 TO MODENA C E 

 

 

 

 

 

 

5.

 

Lay the boiler on its back. Remove the front casing 

panel  by  undoing  the  two  securing  screws  on  the 
underside  of  the  case.  Ease  the  lower  edge  of  the 
panel  forward  to  clear  the  controls  display  and  lift 
upwards off the frame. 

 

 

 

 

 

 

 

6.

 

Lift  the  boiler  onto  the  hanging  bracket  making 

sure  the  lugs  on  the  bracket  locate  correctly  with 
the two support brackets on the boiler frame (Fig. 6) 

 

 

FOR STANDARD HORIZONTAL TELESCOPIC FLUE INSTALLATIONS  

Fig.6 

 

UNPACK THE NEW TELESCOPIC FLUE KIT: 

CODE - 041049G0

 

 

 

 

 

7.

 

Remove the protective adhesive cover from the top of the boiler to expose the flue/fixing holes. 

Secure the new appliance flue bend to the top of the boiler using the screws and gasket provided 

 

 

 

 

 

 

 

8.

 

From  the  outside,  push  the  flue 

terminal length  through the  existing 

hole  in  the  building  fabric  and  align 

with the appliance bend. 

 

Lubricate  the  seal  with  a  suitable 

silicone  grease  and  push  the  flue 

pipe fully into the into the appliance 

bend.  Ensure  the  flue  terminal  is 

fitted level 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Level 

 

 

Содержание MODENA 27 C HE

Страница 1: ...Ferroli Modena HE 21st Century Design for 21st Century Life ...

Страница 2: ... left of the existing boiler no alteration to the existing flue position is necessary Please note As with all condensing boilers it is necessary to check the existing flue terminal position to ensure that the plume from the combustion products will not create a nuisance problem A plume displacement kit is available to overcome any such problems Consideration must also be given for the provision of...

Страница 3: ... securing screws on the underside of the boiler Ease the lower edge of the case forward to clear the controls panel and lift the case upwards off the retaining lugs Fig 1 Case Securing Screws Fig 1 2 Safely isolate the electricity gas and water supplies to the appliance Completely drain the boiler and central heating system and disconnect all existing pipe work connections from the underside of th...

Страница 4: ...and check the contents are complete and undamaged see opposite Please note The new flue kit is sold separately 3 Align the fixing template on the wall with the existing flue hole ensuring it is level both horizontally and vertically Check for required minimum clearances then mark the most suitable fixing points for the hanging bracket It is advisable to mark the position of the gas water and heati...

Страница 5: ...er frame Fig 6 FOR STANDARD HORIZONTAL TELESCOPIC FLUE INSTALLATIONS Fig 6 UNPACK THE NEW TELESCOPIC FLUE KIT CODE 041049G0 7 Remove the protective adhesive cover from the top of the boiler to expose the flue fixing holes Secure the new appliance flue bend to the top of the boiler using the screws and gasket provided 8 From the outside push the flue terminal length through the existing hole in the...

Страница 6: ... A and fit the condensate bowl and washer Push on the rubber condensate hose to the trap outlet Fig 9 B Fig 8 Cut existing pipes back approx 200mm 300mm Condensate bowl washer and rubber hose connection Connect the safety valve outlet Fig 9 C to the existing 15mm pipe and then connect the condensate pipe to the rubber hose outlet Check that both terminate in accordance with BS 6798 Take care not t...

Страница 7: ... work by opening all the hot taps 13 Reinstate the gas supply purge and test in accordance with BS 6891 and IGE UP 1 14 Connect the boiler to the electrical supply the boiler is provided with a 1m cable and plug Reconnect any external controls to the volt free terminal block in the boiler To access the connections remove the securing screw and hinge the controls cover to the left Connect the exter...

Страница 8: ... note there may be a pressure loss across the isolation valve to the gas valve inlet test point of up to 1 3 mbar at maximum Remove the manometer re tighten the inlet test point 14 Measure the gas rate of the boiler and check against the following table 15 Connect the flue gas analyser to the flue sample point Fig 15 with the boiler still in TEST MODE check that the readings are within the toleran...

Страница 9: ...Ferroli 21st Century Design for 21st Century Life www ferroli co uk 0843 479 0009 Ferroli Limited Lichfield Road Branston Industrial Estate Burton upon Trent Staffordshire DE14 3HD Modena HE ...

Отзывы: