Step 14 – Fit Roof Sheeting 

Lay the first sheet in position and ensure that the roof sheet is flush with the outside face of the 

rafter on the high end. This edge of the rafter should be pan fixed using 10-16 wall screws to aid in 

the fitting of barge capping. If the frame is square, the first sheet should now be flushed along the 

length of the rafter. All other sheets may now be fixed at crest with the number of screws per sheet 

at supports specified on the Engineering Plans. Ensure that roofing sheets are turned up at the high 

end to prevent water running off this end.  

 

Step 15 – Fit Gutters and Flashings 

Remove plastic cover protecting gutters and flashings before they are fitted.  

a)

 

Fit the cover flashing to the gutter end of the roof 

b)

 

Fit the stop ends and nozzle to the guttering 

c)

 

Fit gutter brackets to the cover flashing with pop rivets. Ensure the brackets are fitted with a 

string line to the required fall location. 

d)

 

Fit the gutter brackets into the gutter 

e)

 

Fit side and head barge flashing and ensure that the bottom edge of the flashing is fixed to 

the bottom lip of the C-Purlin with pop rivets. 

Step 16 – Cut and fit downpipes 

Cut and fit the downpipes to the drainage system. 

Step 17 – Finish 

Remove any temporary bracing and check that all the required bolts and tek screws are fitted and 

tightened.  

BRUSH COMPLETE CARPORT DOWN WITH A SOFT BROOM TO REMOVE ANY METAL 

DUST/FILINGS CAUSED BY ANGLE GRINDER. 

CONGRATULATIONS ON A JOB WELL DONE! 

Содержание FLAT ROOF CARPORT

Страница 1: ...FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL This document remains the property of FBHS Aust Pty Ltd Feb 2019 Version 2...

Страница 2: ...port Posts 5 Step 4 Post Sleeve on Base Plate Set out 6 Step 5 Preparation of Rafters 7 Step 6 Assemble and Stand the Carport Post and the Rafter 8 Step 7 Fixing of the Beam 9 Step 8 Fixing of Roof Pu...

Страница 3: ...essional advice to ensure your needs are adequately met b Check with your local government of any approval or restriction requirements It is your responsibility to ensure that all approvals required a...

Страница 4: ...ing the string set out of the perimeter as a guide edge of the post is set in on the sidewall by the flange width of the Rafter To determine the centreline of the post add 1 2 of the post size to the...

Страница 5: ...efer to Engineering Plans for the actual size and specifications of your specific job As a guide edge of the post is set in on the sidewall by the flange width of the Rafter plus the 100mm slab extens...

Страница 6: ...LOCK footing and edges of concrete for SLAB to be left in place until the position of base plates are clearly marked Step 3 Preparation of Carport Posts Check levels of footings and if required cut po...

Страница 7: ...ews is to be fixed in lieu of the bolt holes Refer to Diagram C You may stand the plumb post into the excavated holes and pour concrete at this stage or go to Step 5 to bolt the eave purlin to the pos...

Страница 8: ...post sleeve Step 5 Preparation of Rafters On the outer web side of the Rafters set out and attach the shorter leg of the angle cleat bracket with 2 frame bolts This bracket will be fitted inside the w...

Страница 9: ...post in footing holes if embedded or insert the post over the post sleeve with base plate if not embedded Refer to the Engineering Plans for specific footing requirements Plumb the post and hold in pl...

Страница 10: ...ins and the outer web of the Rafter The beams at the low and high ends have the open side of the C Purlin face out Refer to Step 12 3D View Step 9 Plumb the Posts Plumb the front posts on one side and...

Страница 11: ...als are equal is to calculate using this formula Diagonal square root length2 width2 Step 12 Complete Fixing of the Frame On the side that is on props fix the remaining two posts to the Rafter Plumb t...

Страница 12: ...along the sidewall between the outer flange of the end posts and the web of the rafter on 1 side only Refer Diagram M The endwall will have the gusset plate between the inner flange of the end posts...

Страница 13: ...12 This document remains the property of FBHS Aust Pty Ltd Feb 2019 Version 2...

Страница 14: ...tters and Flashings Remove plastic cover protecting gutters and flashings before they are fitted a Fit the cover flashing to the gutter end of the roof b Fit the stop ends and nozzle to the guttering...

Отзывы: