BURY LINE
Figure 5
4.
Mix concrete per the instructions on concrete bag. Pour into the hole
and stop about 16” from Playing Surface or until you can still see the top
of the Masonry block you placed earlier. See
Figure 5
and
Detail 1
.
5.
Set the bottom of the pole on the masonry block in the hole. Make
sure the Pole stays on the block as shown in
Figure 5
. The Bury line
should be level with the playing surface see
Detail 1
.
While one person holds the pole in place have two other people finish
pouring concrete up to court level. Use a level to make sure Pole is vertical.
6.
Detail 1
PL
AY
IN
G S
UR
FA
CE
IMPORTANT
BE SURE THAT THE HOLES ARE TOWARD THE
BACK OF THE POLE AND “BACK SIDE”
STICKERS ARE AT THE BACK OF THE POLES/
OPPOSITE THE PLAYING SURFACE BEFORE
POURING CONCRETE ON STEPS 4-6.
(Court Level)
THE FOLLOWING STEPS WILL REQUIRE
AT LEAST THREE CAPABLE ADULTS.
IMPORTANT
16"
PLAYING SURFACE